what is meant by bus bar and outgoing/incoming breaker in
an electrical/electronic circuit
Answer Posted / prashant
from the main distribution panel (MDB)the cables are taken
to the various SUB MAIN DISTRIBUTION PANELS (SMDBs)located
in the various typical floors or other locations. Normally
we can use cables for this purpose but in situation swhere
the the building is more than 15 - 20 floors it is more
economical to use BUSBARS.Busbars are nothing but CU
conductors and normally one RYBN section ( 4 poles but
actually neutral is only half ie, 3.5 poles )can feed up to
8 - 9 floors. In every floor there will be a tap off box
from where normal cables are used to till the SMDBs.
A breaker is sed to break the circuit in case of any faults
or for maintenance purposes. Incoming braeker is one which
is given before the transformer side and the outgoing
breaker is given after the transforemer side ( ie secondary
side ) Normally in case of maintenence we can only turn off
the outgoing breaker
| Is This Answer Correct ? | 10 Yes | 0 No |
Post New Answer View All Answers
transformer spections :: input voltage 0-110-230v; output volage 0-10-12-14v; amp=3A using CRNO CORE, capcaity=50VA primary turns = ? ; secondry turns =?
How can ou verify the size of conductor 50Sq.mm ACSR
what the principle of sincroscope?how it works?when it needed?
WHAT IS MEANT BY SHEATH VOLTAGE IN 132Kv cable?
what reactive how to maintain
May I know how much values to be set for earth fault, over current and short circuit values at 11kv side? I have 11kv van 1250amps rating. Present it's taking load 80amps?
do any one help me to get "C" license,, i have doubts ,,, if mediators ter pls call me,, my no is 8056640042
why to use freewheeling diode ( diode in revers bias mode) across dc coil
How to work E.L.C.B and how to connect in circuit.
how many types control panel of a 132/33 kv substation
wat is the first thing dat is needed, 2 lay a cable in some area??
Why is the air gap between the pole pieces and the armature kept very small?
what is ground fault in ACB?
What are the different circuits in thermal power plant?
Describe the control mechanism of missile launcher???