Whats meant by trivector meter where it is connected at the
substation?
Answer Posted / shanker malagamma
yes, indeed trivector means the which measures energy in
three vector i.e active energy(kwh), reactive energy(kvarh)
and apparent energy(kvah) using single meter and it is
connected to incoming and outgoing feeders in the
substaion. Trivector meter may in four quadrant or may not
be four quadrant, if it is four quadrants then it is called
as Trivector meter with import-export facility or if it is
in any two qudrants i.e either import only two qudrants or
export only quadrants then it is called as TVM with import
only facility or TVM with export only facility. normally
former one will be manufactured than later.
Is This Answer Correct ? | 25 Yes | 23 No |
Post New Answer View All Answers
What is shutdown of electrical sub station?
What is mean by spike arrester(Voltage Operated)
Why is a plain induction motor unsuitable for wide speed control?
how to select the double earth conductor if 21A full load?
how many electricity poles are there and what are the names and their sizes.
what is the difference between pvc & fiber glass cables
A 11KV, 1200 A breaker combination fixed in a cubicle for HT motor.Is normally for 11 KV motor fuse is using? if Yes, What range fuse is required?
What aturn on methods of scr?
What is the armature mmf in a D.C machine?
why on delay timer used for fully automatic star delta starter?
I want to put this query to SENIOR & EXPERIENCED ELECTRICAL ENGINEERS. 1)I want to know about the control circuit diagrams for control panels. I found it difficult to understand. Is there ant booklet through which we can learn the circuit diagrams? 2)I want to learn about conduiting, laying cables, preparing cable schedules and various techniques which is the part of building infrastucture(construction field). I don't have any experience in this area. I have experience in control panels only. that's why i am not getting any opening in building infrastucture (construction field).Can I get the job in this field as Trainee Engineer? How to enter this field? I need job in PUNE
WHAT IS MOBILE SUB-STATION? & REALLY BENEFIT IN INDIA
Mention the disadvantages of low power factor? How can it be improved?
When color of silica gel will gets change from blue to pink from Top to bottom?
i need to give section engineer (electrical engineer) for RRB. Please suggest some book