Answer Posted / hemant gor
A 615 is a high carbon steel. As you have seen in other posts, A615 IS technically weldable, but A615 is not widely welded because of the procedure requirements to weld it.
Generally A706 is specified for weldable rebar to avoid the AWS welding procedures required for A615 rebar.
| Is This Answer Correct ? | 5 Yes | 0 No |
Post New Answer View All Answers
how many kg of 20mm, 10mm, dust available in one ton stone boulder
is concealed wiring a problem in fly ash brick wall?
Explain what is 1/8 on the architect ruler denotes?
how to calculate testing date
Kindly post me previous year interview questions with answer for post of DY. Manager (civil engg.) for GAIL, NTPC, IOC, OIL and ONGC etc.
a sewer which receives the discharge of no. of house sewer is called house sewer lateral sewer intrcepting sewer sub-main sewer
I am called for interview from north east power plant .so, I need some interview question which may help me.
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
reinforcement slab, beam and column formulas?
1.what is the mix proportion for cement soil compressed earth blocks? 2.how to calculate the mix proportion for cement stablised earth soil blocks?
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3
beam length 73 feet 4 inch,width 01 feet,height 50 inch so every beam load how much? and what quantity of M.S ROD? both side ony two column in middle no column.pls inform me that this is stable or not ? and how much risk of this beam?
How to calculate volume of concrete & steel on tank foundation & ring wall ?
how to calculate total cost for slab 35'×8'
Cut Linten (RCC-1:2:4)on 10" wall - what should be the width and hight of cut Linten? Secondly, 1 X 1.6 foot,4" thick window sun/rain shed (Chajja)should consume steel,Cement, sand and Stone chips?