Answer Posted / mohd mansoor
The diferece is all about their arc quenching medium
MCCB-moulded case circuit breaker ..here arc is quenched by
the special designed case of switchgear
ACB-Air circuit breaker ..here arc is quenched in a medium
by the force of air
VCB..(Vaccum Circuit Breaker)...here arc is quenched in
vaccum medium
And their use depends upon the amount of current to be
isolated ...Like ACB is used where the load current is more
then 1000A..MCCB is used in a range from (63A to 800A) and
VCB is generally used at HT side
| Is This Answer Correct ? | 29 Yes | 6 No |
Post New Answer View All Answers
what is meant by brushed alternator & its working principle ?
What are the types of windings present in the ceiling fan? What winding will be effective first when we started the fan?What are the resistance and inductance ratios comparatively at the initial speed and full speed of the fan?
what is allowable ac mixing in dc
What is cable tray, its type, and its support?
I am getting above 60 V as open delta voltage against single phase unit ICT at tertiary delta formed and ICT getting trippped on NDR. ICT tested and found in order. PTs provided on tertiary are tested and in order. what may be the reason?
How to calculate the Harmonics losses in terms of cost/unit.
how to calculate the breaking capacity of different breakers.
Could u pls tell me the NPCIL electrical engineering interview questions for Executive trainee, and also guide me how to face the interview.
What are :- AC Distribution Board (Single & Double Front) DC Distribution Boards Distribution Board LT Breaker Panel.
how to work droop ct in generating station
Can any one provide the inspection procedure of MIMIC for VFD panel? Details: If someone wants to have a mimic in the VFD panel what are inputs considered for the mimic(like on,off,trip) whether we are able to add speed variation in the mimic(if so how can we get) and what are the parameters to be checked in the MIMIC during inspection?
why we can use 1 to 5V dc
what is level 2 automation?
We have received supplies of the ordered material. payments against the supplies also released. Where ST paid 4% against form C. Meanwhile it has been observed that 25% of material supplied was defective. Please suggest whether the issuance of C form from our side would be stopped till settlement of liabilities.
redundant connection in contactor?