OLTC MEANS ON LOAD TAP CHANGER. THE LOCATION OF OLTC IN
TRANSFORMER IS IN HV WDG. THE TAPPING IS TAKEN FROM HV WDG
B COZ
1. IN HV WDG NO. OF TURNS ARE MORE. SO,VOLTAGE REGULATION
IS GOOD.
2. THE HV WDG IS NEARER TO THE CORE. SO, THE TAPPING IS
POSSIBLE.
3. IN HV WDG CURRENT CARRING CAPACITY IS LESS THAN LV WDG.
THE FUNCTION OF OLTC IS TO GIVE CONSTANNT VOLLTAGE TO
SECONDARY WDG.
PLEASE GIVE ANY ANSWER THEN WELCOME
ANY DOUBT E MAIL ME. ON SABALE.DNYANESHWAR@GMAIL.COM
Is This Answer Correct ? | 206 Yes | 45 No |
Post New Answer View All Answers
solar energy light efficiency & disadvantages?
Show the schematic arrangement of diesel power station layout and give its principle of operation.
Define conversion efficiency of a power amplifier.
what is V.L.F. testing of power cable? do you know the voltage ratings, like for what rating and size of cable what rating of V.L.F. testing is used?
in cvt,there are two windings,1a,1n and 2a,2n.in my one project i use only one winding i.e.1a,1n. the other winding is not in use, so i connect it in open delta and want to close it by ibsertibg thermal resistor. the output of cvt is 132kv/115/sqrt3. plesae tell me exact value of resistor, so i may close it to avoid the resonance phenomenin. send me answer on this email adress please. aetcon-po@aetcon.com
how is capacitor bank look like
What are the major reasons for balancing hydro-thermal mix?
What does ampere turns shows?
What is reverse power relay?
Is it possible to download the Siemens Selection Chart(TYPE 2 coordination) for 1) fuseless selection 2)Fuse selection
distribution transformer de-rating formula on over limit iron losses
Pl.brief me about Electrical power distribution system from Main generating station to Industry.What is the use of in between station.
sir,in our plant we r using SATEC PM172E power reading meeters in HT panel side it is monitoring the MB data smart viewer(sever).but last one week we did not get readings inthe server only available in meeter.tell me how communicate meter and server. and also what steps we take for checking.
while doing high voltage test on 11kv/433 distribution transformer why we only give 28 kv on hv side and 3kv on lv side for power transformers what is the value what factors it depends
Can I use distributon class/transmission class Lightning arresots for protecting the building? If not why please explain?