Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how we can calculate the transformer size.

Answer Posted / sachin

actually at the time of transformer rating decided the
following factor to be consider
1.Connected Load
2.Power fACTOR
3.fUTURE eXPANSION

KW=KVA*P.f
630=KVA * 0.8
KVA = 630/0.8
KVA = 787.5 KVA

So the Transformer size is 800KVA

THIS CALCULATION IS EXACTLY CORRECT

BUT FOR FUTURE EXPANTION WE CONSIDER 30 % MARGINE FOR THAT

Is This Answer Correct ?    80 Yes 13 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the role of power pack in substation protection system?

2634


what is the star delta connetion and how can do it a three phase motor with control witing with picture

2216


what is the standard values(Megger test) of resistances between L&N,L&E and N&E for a system on IEE regulations?

2201


How to calculate of maximum demand if given 628kw, 785kva, 0.8 p.f.

1590


what is the ATS .And how it works.

1545


what is the difference between switchgear and circuit breakers and is there any difference between outdoor and indoor switchgear and circuit breakers , and how would you differentiate between switch yard and substation and grid station . thanks

2167


What are the reasons for the parallel operation of transformers?

1077


What is an 86-P or an 86-A trip

2023


Hi Friend I am used multimeter to measure the voltage between R Phase(SS1) to R Phase(SS2). In SS1 is connected with UPS loads. But I am getting voltage between these 2 R Phases. Please give some idea friend

2002


What is reactance, reluctance,capistance, pls give answeer in hinglish and be simply Jo asani we smajh m aa jaye

2049


i have seen one 8.4 MW synchronous motor in a plant located in bellary it is fixed with brushless rotary rectifier ,anybody can explain its start up principle

1923


An impedance of 100 ohms resistance and an unknown inductance is connected across the capacitor. The resulting impedance is a pure resistance of 500 ohms ifω = 10^5 rad/sec. calculate the values of inductor and capacitor.

1354


what is a vector protection in transformer

1963


What is the estimated total hydropower potential of india?

1085


Please clarify, 1. Is it required to lay two runs of GI wire along with Armoured LT cable if it is laid between one big mains (63Amps TPN SDF) to small main (32A TPN SDF) with proper glanding termination? 2. If the armoured cable with proper glanding is laid from DB to CNC machine, is it required to run two runs of body earthing to the Machine from DB? 3.If the armoured cable with proper glanding is laid from Substation to Hangar, distance is approx. 100 mtrs, is it required to do earthing at shop area though the primary termination at substation is earthed through gland.

1988