Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

how we can calculate the transformer size.

Answer Posted / sachin

actually at the time of transformer rating decided the
following factor to be consider
1.Connected Load
2.Power fACTOR
3.fUTURE eXPANSION

KW=KVA*P.f
630=KVA * 0.8
KVA = 630/0.8
KVA = 787.5 KVA

So the Transformer size is 800KVA

THIS CALCULATION IS EXACTLY CORRECT

BUT FOR FUTURE EXPANTION WE CONSIDER 30 % MARGINE FOR THAT

Is This Answer Correct ?    80 Yes 13 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What are the different types of hydro schemes?

1251


at which voltage level arcing ground is occurs ??????????

2065


Which device is used for the source of emission of electrons in a crt?

1268


why capacitive load is not used in routine life????any reason is there ??????

1769


What is meant by impedance? difference between high & low impedance ?

2060


what is the meaning of vcc

2514


The advantages of Magnetic flux leakage technique over Ultrasonic technique for non distructive testing of material.

1978


I need to connect a synchronous generator to the grid using automatic synchronization and two circuit breakers (one for synchronization, one for end connection to the grid), how to determinate the required diameter of the cables?

2219


when measure the core loss of three phase distribution transformer or three phase reactor loss, one phase shown negative watt loss. why??

1971


Dear sir, In our plant have Station Transformer having capacity,i want to know, why LV side 40 - 40MVA is given? & how we can get 6.3 KV supply from tertiary(i.e. Open delta connection), Vector Group YNyn0 - yn0 +d MVA Rating 80MVA / 40 - 40MVA + 26.7MVA Voltage rating 420 (Tap range +6,to -10)81.25% /11.5KV - 11.5KV +6.3KV

2168


How is operate breaker failure scheme in substation

2117


what is calculation mathod/formaulla for deciding Size of busbar (Copper/ aluminum)for L.T. panel on Various Fault level like 50kA,25kA,10kA

2797


How good are you in resolving the commercial issues to Employer's advantage?

2360


what could be the RMS value and average value of a 4 phase sine wave?

1880


In our factory so many iron pillors are exists for supporting the shed/Hangar. If do more no of earthings at one piller instead of doing more earth pits in many locations and running earth strip around the hanger, I can save the money. Please suggest this method is acceptable as per Is specifications though the Earth resitance of the farthest piller is with in the limits as per IS specifications.

2122