Answer Posted / abhinav yadava
Dyn11 is vector group notation of tansformer.It means LV
winding,which is star connected (written in small letters
means LV side and vice versa)is 30 degrees lagging by HV
winding which is delta connected.In India we go for +-30
deg connection of transformer.
Is This Answer Correct ? | 131 Yes | 49 No |
Post New Answer View All Answers
defination of controlled shunt reactor
What are the various kind of cables used for transmission?
What is float cum boost charging system?
ANY ONE TELL ME ABOUT generator synchronization panel panel to synchronise 3 gen of 250kva both automatic and manual. 2 gen output vol 415 3ph, 1 gen output vol 400 3ph SEND THE DETAILS DIAGRAM ON THIS EMAIL ADDRESS ayazleo@hotmail.com as soon as possilble best ragrds electrical engineer ayaz mahmood SAUDI TECH
Why ground terminal is used in pot meter 10k ohms
how can service sitting be setted for MCCB?Example for sittings IR (CURRENT RATING),IS(CURRENT STARTING)IO (current operating
what is working process of star delta controlling circuit ?
How to address the servo drive for motor
High voltage test procedure of in swgr board. why should measure millivolt drop on testing time?
Please help me regarding my one concern. - During earth pit testing we noticed that the Clean earth pit and dirty earth pit showing continuity (Resistance value - 5ohm) . I want to know that if both earth pit have separate location and there is not internal looping between PIT then why such continuity is showing on it . Because of this issue the field side all earthing point showing short. In PLC panel we are providing two types of earthing cable which is coming from separate earth pit (Clean and Dirty earth pit) because of earth PIT showing short our PLC is not complying spec . please help regarding this issues.
how to interlock 3 nos MCCBs using under voltage coil. please provide me circuit diagram?
why co incidence factor considered in transformer sizing?
explain the Trip supervision circuit
What are the Formula of computing Back up Time of 500kVA UPS with 4 Battery Banks, each bank composed of 43 pcs of Batteries 12V150Ah. How to compute the Back up Time of UPS? We have also 3X500kVA UPS running in Parallel same composition as I write above.
How to measure current and voltage in an ELV circuit