Which of the following is constraint chat you might find during the Organizational Planning process? A. Organizational structure, expected staff assignments, collective bargaining agreements, and project management team preferences B. Organizational structure, organizational interfaces, technical interfaces, and interpersonal interfaces C. Organizational interfaces, expected staff assignments, collective bargaining agreements, and project management team preferences D. Organizational interfaces, technical interfaces, and interpersonal interfaces
You are the project manager for a scheduled version release of your company’s software tracking product. You have linked the WBS and project scope definition and assigned roles and responsibilities. You might want to display the roles and responsibilities in which of the following? A. RDM B. PDM C. AOA D. RAM
Which of the following is true regarding the staffing management plan needed for project activities? It is an output of the Resource Planning process. A. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Resource Planning process. B. It details how and when staff resources will be brought on and take off the project. It is an output of the Organizational Planning process. C. It details how and when staff resources wilt be brought on and take off the project. It is an output of the Resource Planning process. D. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Organizational Planning process.
All of the following describe the activity list except: A. It's an extension of the WBS. B. It includes all activities of the project. C. It describes the WBS updates. D. It includes a description of project activities.
You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery score chain. You have your activity list in hand and are ready to diagram the activity dependencies using the PD technique. You know that: A. PDM uses AON diagramming methods. B. PDM uses AOA diagramming methods. C. PDM uses ADM diagramming methods. D. PDM uses PDM diagramming methods.
You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have your activity list in hand and several time estimates and are ready to diagram the activity dependencies. You should use which of the following? A. PDM techniques B. PDM or ADM techniques C. AON techniques D. ADM techniques
All of the following are true regarding the tools and techniques of Activity Sequencing except: A. GERT uses analogous methods. B. GERT allows for loops. C. GERT is a conditional diagramming method. D. GERT allows for conditional branches.
You are the project manager for Changing Tides video games. You have produced a project network diagram and have updated the activity list. Which process have you just finished? A. The Activity Sequencing process, which identifies all the specific activities of the project B. The Activity Sequencing process, which identifies all the activity dependencies C. The Activity Duration Estimating process, which diagrams project network time estimates D. The Activity Duration Estimating process, which identifies all the dependent activities of the project
You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time
As project manager, you know that all of the following are true concerning analogous estimating techniques except: A. It's a qualitatively based estimating technique. B. It's a top-down estimating technique. C. It's a tool and technique of Activity Duration Estimating and Cost Estimating. D. It’s a form of expert judgment.
You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following? A. Preferential logic B. Soft logic C. Discretionary dependency D. Hard logic
You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time
Your project sponsor has requested a cost estimate for the project. She would like the cost estimate to be as accurate as possible as this might be her one and only chance to secure the budget for this project due to recent cuts in special projects. You decide: A. To use analogous estimating techniques B. To use bottom-up estimating techniques C. To use top-down estimating techniques D. To use expert judgment techniques
Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use: A. Analogous estimating techniques B. Bottom-up estimating techniques C. Parametric modeling techniques D. Computerized modeling techniques
All of the following are true regarding parametric modeling except: A. It's a form of top-down estimating. B. It's a mathematical model. C. It's a tool used to estimate project costs. D. It's a tool used to estimate project time.