How many cement bags of 50Kgs will be required for 2600sqft terrace with thickness of 5".
Answer Posted / nuhannad tufayl
163.8 bags of cement required. as follows;
2600 x 0.42 = 1092 cft
0.15 bag use in 1-cft so
1092 x 0.15 = 163.8 bags used in 1092 cft volume.
| Is This Answer Correct ? | 3 Yes | 1 No |
Post New Answer View All Answers
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
is it fair to recruit another prestressing agency once earlier agency has provided guide cone for post stressing the Concrete -I girders? It is observed that the bearing plate of another agency is not matching with the earlier one resulting in protruded strands after stressing from the face of girder. Kindly advice.
How to Know that veriation acceptable in CPWD Work Of 1:6 Cement Mortor Received Lab test report.
With reference to construction of state highways, please let me know the total Bill Of Quantities as per the following details:- 1) Subgrade - 500 mm 2) Granular Sub-Base (GSB) - 200 mm 3) Wet Mix Macadam I (WMM I) - 150 mm 4) Wet Mix Macadam II (WMM II) - 100 mm 5) Dense Bituminous Macadam (DBM) - 60 mm 6) Bituminous Crust (BC) - 40 mm Road Length is 44 Kms. Road Width is 7 mtrs. Please provide the BOQ of each layer as per Compacted Factor & Loose Factor both. Also, if possible please provide me the approximate details of total material required (all categories viz. soil, gravel, stone aggregrate, sand, bitumen etc.) as per general mix design prevailing in India. Thanks & Regards -- Rokr
what is the most suitable foundation when construct a bird watching tower in a marshy land
What is an ice dam sock?
How to find out kg per Sft ?
one steel fixers how much ton steel fabrication he will do same how much tone he will binding?
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3
primary treatment of sewagw consist of removal of floating materials removal of sand & grit removal of organic materials all above
if in column reinforcement lower dia connect to higher dia then from wher we want to start higher dia steel
List out some of the common problems that architect have to tackle it?
how many numbers of 4inch bricks and get consumed in 9 inch BB masonary wall in cubic feet.plz send my below e.mail adress
why is M25 and Fe 500 assumed to be most economical? i feel it is not.This is because higher grade of concrete and steel has higher lapping length and anchorage length compared to lower grades..
importance of the soundness test to determine the quality of cement use for any construction