How to set up the various advanced process controllers,
input the proper parameters, and tune those controllers
given related control system information.

Answer Posted / jobby c johnson

in process control selection of a particular controller is
based on the application and what are process parameters that
you are going to measure.
based on the external conditions you have to design the data
acquisition system. some times the voltage level will not be
matching, so you requires a voltage translators(eg:).

there will be a process requirement saying that you need the
overall response of the system with in this much time, with
minimum error etc based on those parameters you have to tune
the controller parameters.

Is This Answer Correct ?    1 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the use of GMV in turbine?

3732


hello can yoy pls send me previous papers of jindalpower and steel ltd.....'m from instrumentation..... mani1048@gmail.com

1583


What inherent design and operating principles are included in a modern control system to use predictive maintenance practices to increase overall system reliability?

1605


applications of plc in printing and packaging?

1678


why we should maintain neutral earth voltage below 1V while calibration? why cant it be 1.2V or 2V

2002






What should be the main consideration while starting the Rotating compressor when we dont know the cut in and the cut off pressure setting of the pressure switch

1699


what is the procedure of O2 sensor(ABB) calibration?

1710


I have completed B.E. Instrumentation & control in 2009. i have 3 year industrial job experience in chemical plant.now, I want to join M.E. in external. so, Plese say easiet way and good institute name.

1474


is there any digitel grevity meter availaible in the market by which we can measure specific gravity of a battery?

1797


What is difference between “Fault Tolerant” & “Fault avoidance” PLC? Application where these system s are used?

3443


There are two chlorination tonners both are connected to two pressure swithes and the pressure switch is connected to SOV which operates the valve to changeover the tonner selection i.e if pressure one tonner goes low the other tonner should come in line if it is inautomatic selection design a circuit using relays ?

1459


WHAT IS MEANT BY PROJECT MANAGEMENT STRATEGIES IN INSTRUMENTATION?

3036


How to Calibrate Coriolis Flow transmitter in field

753


why fuse block is not used for AI signal?

1399


how 3 out of 2 Logic/interlocks works? give brief explanation with help of diagram.

1842