Answer | In The MPS, the comapny level critical components are
planned and in the mterial master, the MRP type is choosen
accordingly, this is generally done for single level. This
is planned seperately and this can be also done using
interactive planning.
In MRP or time phased planning, the BOm is exploded and
netting is done and component level quantity and time
requirements are planned.
Fisrt MPS is done, then MRP is run.  |