How to calculate cement and sand quantities in cement mortar
As 1:1,1:2,1:4,1:6 ? |
|
Question Asked At :: Simplex, No, KNK Nextgen, Kerakoll India Pvt Ltd |
|
Question Submitted By :: banmayank |
|
I also faced this Question!! |
Rank |
Answer Posted By |
| |
Answer |
in cement morter the void between sand and cement is less
and take 25% total wet volume of water.take 10 cu m wet
volume of morter increse 25% than total volume of dry
material 12.5 cu m . if we find the material in 1:6 morter
than 12.5/(1+6)
cement=1.78 cu m sand=1.78*6=10.71cu m
|
|
Kamlesh Patidar
|
| |