Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.

Answers were Sorted based on User's Feedback



Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / kishore kumar

Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will
be
= 2x1.7x0.15 + (0.5-0.15)/3 x ((0.3x0.3+2.0x1.7+sqrt
((0.3x0.3)(2.0x1.7))
=0.981 m^3

Is This Answer Correct ?    98 Yes 37 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / vishal gajjar

h(=D-d)\3 * A1+A2+SqrtA1A2 = Q1
A1*A2*thickness = Q2

Q = Q1 + Q2.

Is This Answer Correct ?    40 Yes 11 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / suresh,trichirapalli

Q1=2.1*1.7*0.5
Q2=(0.5-0.15)/3*((A1+A2)+(SQRT A1*A2))
A1=Area of bottom portion
A2=Area of top portion
TOTAL QTY=Q1+Q2

Is This Answer Correct ?    22 Yes 8 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / s s grewal

Before calculating the quantity of concrete required for size of pillar or size of footing at (D=0.5 m)



Formula :- L X B X d + D-d/3 x A1 + A2 + √(A1 X A2)

Is This Answer Correct ?    22 Yes 9 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / manpreet singh

suppose area at bottom A1 = (AxB) and area at top A2 (axb), where A,B,a,b are the respective lengths of footing top and bottom. further D is total depth and d is small depth of footing

formula is A1xd + (D-d)x(A1+A2 + sqroot {(A1xA2)/3}

Is This Answer Correct ?    18 Yes 11 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / r. dilli babu

Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will be
=h/3(A1+A2+Sq root of A1square+A2square)
=((.5-.15)/3)(.09+3.4+(sq root of(.09 square + 3.4 square)))
=.116(3.49+(sq root of (11.5681))
=.116(3.49+3.401)
=.116*6.891
=.799 cum

Is This Answer Correct ?    8 Yes 4 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / sagar mistry

Here you have not given the column size.
So we assume column size 300mm X 300mm.
There is an Offset after the periphery of column & it is 75mm.
Rectangular Part
=L X B X H
=2 X 1.7 X 0.15
=0.51 cum
Trapezoidal Part
=(h/3)(A1 + A2 + SQRT ( A1 X A2 )
=((0.5-0.15)/3) ((2 X 1.7) + ((0.3+0.075)+(0.3+0.075)) + SQRT ((2 X 1.7) X ((0.3+0.075)+(0.3+0.075))
=0.12 ( 3.40 + 0.75 + 0.70 )
=0.57 cum
Total Concrete
=0.51 + 0.57
=1.08 cum

Is This Answer Correct ?    8 Yes 4 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / ashish parasiya

Question is not complete because one must require top are to calculate volume for trapezoid.

Is This Answer Correct ?    6 Yes 3 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / r. ansari

Formula for trapezoidal footing quantity
Q = h/3{(a+b)+√ab}, a&b is area of bottom and top portion
=0.5/3{2x1.7+0.15x0.15+√3.4x0.0225}
=0.583 Cu.m.

Is This Answer Correct ?    11 Yes 10 No

Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quanti..

Answer / r. suresh

Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will be
=H/3(A1+A2+sq root of A1+A2)
=((0.5-0.15)/3)(3.4+0.09+ Sq root of 3.4+0.09)
=0.621 Cum

Is This Answer Correct ?    4 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

How to calculate density(dry & bulk) of sand from Sp. ravity value of sand. eg. G=2.5

1 Answers  


how many moisture content in well seasoned timber

2 Answers  


5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)

0 Answers   KIOCL,


Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?

3 Answers  


The mixture of different ingredients of cement is burnt at?

0 Answers  






If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)

0 Answers   GeoTechnology,


How you can turn off the display for dimension in CAD?

0 Answers  


why we used shahabad stone (ladi) in box type water proofing.what is the main roll of shahabad stone?

2 Answers  


External staircase area outside the independant house includes in plinth area or not?

1 Answers  


What is the density of Fiber reinforced concrete and give me the which fibers we can use in Concrete?

0 Answers   AltraTech,


what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?

0 Answers   L&T, PIPL,


if 20mm aggregate is coming by weight 25 ton in a 10 wheeler hywa ,then what will be total volume of aggregate in cubic feet.

0 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)