Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete
by explaining all formulas involved.
Answers were Sorted based on User's Feedback
Answer / kishore kumar
Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will
be
= 2x1.7x0.15 + (0.5-0.15)/3 x ((0.3x0.3+2.0x1.7+sqrt
((0.3x0.3)(2.0x1.7))
=0.981 m^3
Is This Answer Correct ? | 98 Yes | 37 No |
Answer / vishal gajjar
h(=D-d)\3 * A1+A2+SqrtA1A2 = Q1
A1*A2*thickness = Q2
Q = Q1 + Q2.
Is This Answer Correct ? | 40 Yes | 11 No |
Answer / suresh,trichirapalli
Q1=2.1*1.7*0.5
Q2=(0.5-0.15)/3*((A1+A2)+(SQRT A1*A2))
A1=Area of bottom portion
A2=Area of top portion
TOTAL QTY=Q1+Q2
Is This Answer Correct ? | 22 Yes | 8 No |
Answer / s s grewal
Before calculating the quantity of concrete required for size of pillar or size of footing at (D=0.5 m)
Formula :- L X B X d + D-d/3 x A1 + A2 + √(A1 X A2)
Is This Answer Correct ? | 22 Yes | 9 No |
Answer / manpreet singh
suppose area at bottom A1 = (AxB) and area at top A2 (axb), where A,B,a,b are the respective lengths of footing top and bottom. further D is total depth and d is small depth of footing
formula is A1xd + (D-d)x(A1+A2 + sqroot {(A1xA2)/3}
Is This Answer Correct ? | 18 Yes | 11 No |
Answer / r. dilli babu
Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will be
=h/3(A1+A2+Sq root of A1square+A2square)
=((.5-.15)/3)(.09+3.4+(sq root of(.09 square + 3.4 square)))
=.116(3.49+(sq root of (11.5681))
=.116(3.49+3.401)
=.116*6.891
=.799 cum
Is This Answer Correct ? | 8 Yes | 4 No |
Answer / sagar mistry
Here you have not given the column size.
So we assume column size 300mm X 300mm.
There is an Offset after the periphery of column & it is 75mm.
Rectangular Part
=L X B X H
=2 X 1.7 X 0.15
=0.51 cum
Trapezoidal Part
=(h/3)(A1 + A2 + SQRT ( A1 X A2 )
=((0.5-0.15)/3) ((2 X 1.7) + ((0.3+0.075)+(0.3+0.075)) + SQRT ((2 X 1.7) X ((0.3+0.075)+(0.3+0.075))
=0.12 ( 3.40 + 0.75 + 0.70 )
=0.57 cum
Total Concrete
=0.51 + 0.57
=1.08 cum
Is This Answer Correct ? | 8 Yes | 4 No |
Answer / ashish parasiya
Question is not complete because one must require top are to calculate volume for trapezoid.
Is This Answer Correct ? | 6 Yes | 3 No |
Answer / r. ansari
Formula for trapezoidal footing quantity
Q = h/3{(a+b)+√ab}, a&b is area of bottom and top portion
=0.5/3{2x1.7+0.15x0.15+√3.4x0.0225}
=0.583 Cu.m.
Is This Answer Correct ? | 11 Yes | 10 No |
Answer / r. suresh
Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will be
=H/3(A1+A2+sq root of A1+A2)
=((0.5-0.15)/3)(3.4+0.09+ Sq root of 3.4+0.09)
=0.621 Cum
Is This Answer Correct ? | 4 Yes | 3 No |
How to calculate density(dry & bulk) of sand from Sp. ravity value of sand. eg. G=2.5
how many moisture content in well seasoned timber
5. Two long boundary walls run parallel to each other at a center to center distance of 1 meter apart. The width and height of the first wall are 0.30 m and 2.5m respectively. While those of the second are respectively 0.18m and 3.5m. Plot the distribution of vertical stress intensity due to walls on a horizontal plane, 1m below ground level. The walls have negligible depth of foundation and are made of brick masonry (y = 19.2 kN/m cu)
Can anybody explain with the help of sketeches that what are 2legged , four legged & 6legged stirrups and how to calculate cut length of diamond ring(stirrups)?
The mixture of different ingredients of cement is burnt at?
If density of cement is 1500 Kg/m3, the how is specific gravity 3.15 ? (Density of water is 1000 Kg/m3)
How you can turn off the display for dimension in CAD?
why we used shahabad stone (ladi) in box type water proofing.what is the main roll of shahabad stone?
External staircase area outside the independant house includes in plinth area or not?
What is the density of Fiber reinforced concrete and give me the which fibers we can use in Concrete?
what is mail role & relationship between senior Civil engineer to consultants , Construction manager ,project manager, project engineer ,Technical engineer & qa/qc engineer ? what is the responsibilites of Senior Civil Engineer?
if 20mm aggregate is coming by weight 25 ton in a 10 wheeler hywa ,then what will be total volume of aggregate in cubic feet.