ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3011)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3270)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13222)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2348)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (407)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (76)
 Bio Engineering interview questions  Bio Engineering Interview Questions (16)
 Metallurgy interview questions  Metallurgy Interview Questions (79)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (162)
 Instrumentation interview questions  Instrumentation Interview Questions (2317)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (104)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (43)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (73)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1189)
Question
Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete 
by explaining all formulas involved.
 Question Submitted By :: Rohit_rangnekar1975
I also faced this Question!!     Rank Answer Posted By  
 
  Re: Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
Answer
# 1
Volume = ((D+d)/2)*B*L
= ((0.5+0.15)/2)*1.7*2
= 0.325*1.7*2
= 1.105 cubic meter
 
Is This Answer Correct ?    41 Yes 66 No
Karthikeyan
 
  Re: Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
Answer
# 2
Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will
be
= 2x1.7x0.15 + (0.5-0.15)/3 x ((0.3x0.3+2.0x1.7+sqrt
((0.3x0.3)(2.0x1.7))
=0.981 m^3
 
Is This Answer Correct ?    70 Yes 29 No
Kishore Kumar
 
 
 
  Re: Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
Answer
# 3
Top Length = L1
Bottom Length = L2
Top Breadth = B1
Bottom Breadth = B2
Depth = D

Then simple formula is
(L1+L2)/2=L
(B1+B2)/2=B
The Quantity of Concrete is = L * B * D
 
Is This Answer Correct ?    15 Yes 46 No
Mohd.younus Ali , Je (pr )
 
  Re: Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
Answer
# 4
suppose area at bottom A1 = (AxB) and area at top A2 (axb), where A,B,a,b are the respective lengths of footing top and bottom. further D is total depth and d is small depth of footing

formula is A1xd + (D-d)x(A1+A2 + sqroot {(A1xA2)/3}
 
Is This Answer Correct ?    13 Yes 7 No
Manpreet Singh
 
  Re: Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
Answer
# 5
h(=D-d)\3 * A1+A2+SqrtA1A2 = Q1
A1*A2*thickness = Q2

Q = Q1 + Q2.
 
Is This Answer Correct ?    24 Yes 7 No
Vishal Gajjar
 
  Re: Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
Answer
# 6
Before calculating the quantity of concrete required for size of pillar or size of footing at (D=0.5 m)



Formula :- L X B X d + D-d/3 x A1 + A2 + √(A1 X A2)
 
Is This Answer Correct ?    17 Yes 5 No
S S Grewal
 
  Re: Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
Answer
# 7
Formula for trapezoidal footing quantity
Q = h/3{(a+b)+√ab}, a&b is area of bottom and top portion
=0.5/3{2x1.7+0.15x0.15+√3.4x0.0225}
=0.583 Cu.m.
 
Is This Answer Correct ?    10 Yes 7 No
R. Ansari
 
  Re: Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
Answer
# 8
Q1=2.1*1.7*0.5
Q2=(0.5-0.15)/3*((A1+A2)+(SQRT A1*A2))
A1=Area of bottom portion
A2=Area of top portion
TOTAL QTY=Q1+Q2
 
Is This Answer Correct ?    16 Yes 3 No
Suresh,trichirapalli
 
  Re: Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
Answer
# 9
Question is not complete because one must require top are to calculate volume for trapezoid. 
Is This Answer Correct ?    2 Yes 1 No
Ashish Parasiya
 
  Re: Trapezoidal footing length = 2m , B=1.7m D=0.5m and d- 0.15m. Can anybody help and calculate quantity of concrete by explaining all formulas involved.
Answer
# 10
Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will be
=h/3(A1+A2+Sq root of A1square+A2square)
=((.5-.15)/3)(.09+3.4+(sq root of(.09 square + 3.4 square)))
=.116(3.49+(sq root of (11.5681))
=.116(3.49+3.401)
=.116*6.891
=.799 cum
 
Is This Answer Correct ?    4 Yes 0 No
R. Dilli Babu
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
How to calculate the amount of Brick,cement & sand required for 1 cum of 230mm thick brick work with ratio 1:5 please give me an answer with detailed step Lanco 10
What is the percentage of steel in 1cu.m. RCC?   4
what is ment by water cement ratio Madhucon 1
Which pavement is advisable in India?(Flexible or Rigid)   6
Water cement mixing in hopper less mixture machine is better than hopper mixture machine because:   1
How much kg of sand,cement will be for 1 sqmt(Blockwork-size 400x200x200)1:4 ratio & same for plaster   2
Can anybody tell me how to calculate the quantity of a trapezoidal footing?With its formula and an example. L&T 9
WHAT IS GROUTING? WHY IT IS DONE? Gammon 9
How do you determine or evaluate success? Essar 5
What is the difference between solids and fluids, in terms of their ability to resist force?   2
during earth quake base shear force=a/w*g Comment? Power-Grid 2
what is the method of all soil testing in lab?   2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   