Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3076)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3289)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13329)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2363)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (416)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (79)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (163)
 Instrumentation interview questions  Instrumentation Interview Questions (2378)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (106)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (43)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (77)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1196)
Question
Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete 
by explaining all formulas involved.
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will
be
= 2x1.7x0.15 + (0.5-0.15)/3 x ((0.3x0.3+2.0x1.7+sqrt
((0.3x0.3)(2.0x1.7))
=0.981 m^3
 
Is This Answer Correct ?    76 Yes 29 No
Kishore Kumar
 
Answer
# 2
h(=D-d)\3 * A1+A2+SqrtA1A2 = Q1
A1*A2*thickness = Q2

Q = Q1 + Q2.
 
Is This Answer Correct ?    26 Yes 7 No
Vishal Gajjar
 
 
 
Answer
# 3
Q1=2.1*1.7*0.5
Q2=(0.5-0.15)/3*((A1+A2)+(SQRT A1*A2))
A1=Area of bottom portion
A2=Area of top portion
TOTAL QTY=Q1+Q2
 
Is This Answer Correct ?    17 Yes 3 No
Suresh,trichirapalli
 
Answer
# 4
Before calculating the quantity of concrete required for size of pillar or size of footing at (D=0.5 m)



Formula :- L X B X d + D-d/3 x A1 + A2 + √(A1 X A2)
 
Is This Answer Correct ?    18 Yes 6 No
S S Grewal
 
Answer
# 5
suppose area at bottom A1 = (AxB) and area at top A2 (axb), where A,B,a,b are the respective lengths of footing top and bottom. further D is total depth and d is small depth of footing

formula is A1xd + (D-d)x(A1+A2 + sqroot {(A1xA2)/3}
 
Is This Answer Correct ?    14 Yes 8 No
Manpreet Singh
 
Answer
# 6
Question is not complete because one must require top are to calculate volume for trapezoid. 
Is This Answer Correct ?    4 Yes 1 No
Ashish Parasiya
 
Answer
# 7
Formula for trapezoidal footing quantity
Q = h/3{(a+b)+√ab}, a&b is area of bottom and top portion
=0.5/3{2x1.7+0.15x0.15+√3.4x0.0225}
=0.583 Cu.m.
 
Is This Answer Correct ?    10 Yes 8 No
R. Ansari
 
Answer
# 8
Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will be
=h/3(A1+A2+Sq root of A1square+A2square)
=((.5-.15)/3)(.09+3.4+(sq root of(.09 square + 3.4 square)))
=.116(3.49+(sq root of (11.5681))
=.116(3.49+3.401)
=.116*6.891
=.799 cum
 
Is This Answer Correct ?    4 Yes 2 No
R. Dilli Babu
 
Answer
# 9
Input is insufficient.size of the column is missing.
If size of the column is 300 x 300 mm, then the volume will be
=H/3(A1+A2+sq root of A1+A2)
=((0.5-0.15)/3)(3.4+0.09+ Sq root of 3.4+0.09)
=0.621 Cum
 
Is This Answer Correct ?    2 Yes 0 No
R. Suresh
 
Answer
# 10
Here you have not given the column size.
So we assume column size 300mm X 300mm.
There is an Offset after the periphery of column & it is 75mm.
Rectangular Part
=L X B X H
=2 X 1.7 X 0.15
=0.51 cum
Trapezoidal Part
=(h/3)(A1 + A2 + SQRT ( A1 X A2 )
=((0.5-0.15)/3) ((2 X 1.7) + ((0.3+0.075)+(0.3+0.075)) + SQRT ((2 X 1.7) X ((0.3+0.075)+(0.3+0.075))
=0.12 ( 3.40 + 0.75 + 0.70 )
=0.57 cum
Total Concrete
=0.51 + 0.57
=1.08 cum
 
Is This Answer Correct ?    1 Yes 0 No
Sagar Mistry
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
where we provide hinged joint in a framee structure ?   3
Difference between Ghol , Chimney & fly ash bricks b)Floor to floor height is 3m , rise=15cm , tread 20 cm , how to design staircase means steps landing   1
what is mean by super structure?   23
what is the allowable silt content in concrete?   6
How you will differentiate in field between grade43 and grade53 catagory cement? Gammon 13
whta are the types of columns   3
what is the weight of concrete for 1 cum? L&T 13
WHAT TYPE OF MATERIALS (CHEMICALS) ADDED IN CONCRETE TO INCREASE THE STRENGTH OF CONCRETE?   2
What is the cement and sand content in the mortar used to build 1 sqm of 190x190x390mm hollow and solid blockworks?   1
wat is the optimum mix design for M25 grade of concrete ? is the ratio 1:1.5:3.65 correct? ACC 6
Quantity of cement in kgs for different proportions and different thickness in plastering work per 1 sq.m. And how to estimate this quantities. L&T 2
what is mean by centrifugal force which is act in vehicle on superelevation of road? Jain-Group 2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   