ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3130)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3300)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13442)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2386)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (420)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (165)
 Instrumentation interview questions  Instrumentation Interview Questions (2402)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (107)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (80)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1204)
Question
Trapezoidal footing length = 2m , B=1.7m D=0.5m and d-
0.15m. Can anybody help and calculate quantity of concrete 
by explaining all formulas involved.
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
i think the dimension what ever is given in the question is not full , because the formula is =
V = [L X B X d] + h / 3 [ A1 + A2 + ROUTE UNDER A1 A2 ]

where ,
l = length , b = breadth , d = bottom depth , h = D - d ,
A1 = bottom area , A2= top area .

so , how can we calculate ,[ A2 ] top area without dimension .
 
Is This Answer Correct ?    259 Yes 36 No
Kumar Biswajit Sinha
 
Answer
# 2
h/3(area of bottom + area of top+ under root area of
bottom * area of top)
 
Is This Answer Correct ?    78 Yes 24 No
Rakesh Suthar
 
 
 
Answer
# 3
volume of trapezoidal footing = H/3{a1+a2+square root a1.a2}
here a1 = area in bottom of footing
a2 = area in top of footing
H = height of footing
if there is any doubt then call me on 09907027855
 
Is This Answer Correct ?    49 Yes 17 No
Santosh
 
Answer
# 4
Concrete quantity = H/3 [ a2 + b2 + square root of a2 x b2]

H = height of the trapezoidal footing

a2 = Area of the bottom of footing

b2 = Area of the top of footing
 
Is This Answer Correct ?    37 Yes 12 No
Sathy
 
Answer
# 5
h/6(a1+a2+4a m),
a1= area of top
a2= area of bottam
am=average of both area
h= height at mid (like:-D)
 
Is This Answer Correct ?    21 Yes 8 No
Abid
 
Answer
# 6
Volume of Trapezoidal footing= h/2(a+b)*l
where,
h= depth of footing
a= top width of footing
b= bottom with of footing
l= length of footing
In Case of Frustrum of Pyramid
V= h/3(A1+A2+Square root of A1*A2)
Where,
A1= Area of top section (a*b)
A2= Area of Bottom Section (A*B)
 
Is This Answer Correct ?    22 Yes 10 No
S.kumar
 
Answer
# 7
from trapezod forula of area a=h/2*(b1+b2)
a=2/2*(1.7+0.5)=2.2m2
from volume formula v=a*d=2.2*0.15=0.33m3
 
Is This Answer Correct ?    2 Yes 0 No
Abiy
 
Answer
# 8
V2= D/6(a1+a2+4Am)where Am=(a1+a2)/2
And D=D-d(total Depth-rectangular Depth)
a1=area Of Footing Bottom
a2=area Of Footting Top

V1=(LxBxd)
V=V1+V2
 
Is This Answer Correct ?    2 Yes 1 No
Kuldeep Yadav
 
Answer
# 9
a1+b1+root of a1*b1*h/3 footing size 7*7m 30cm*30cm
a1=49 b1=0.12m h=.3m
49+.12+root of 49*.012 *.3/3
49.12 + 2.425*.10
51.545*.10= 5.155cum
 
Is This Answer Correct ?    7 Yes 7 No
V.parthiban
 
Answer
# 10
h/3(a1*a2)+root of a1^2*a2^2
a1-area of bottom
a2-area of top
h-over all height
 
Is This Answer Correct ?    1 Yes 1 No
Ananth
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
How much shuttering oil required for per m2 shuttering by 12mm ply   1
what"s the different between OPC (ordinary portland cement) and PPC (pozalana portland cement)? Ashok-Leyland 3
WHICH KIND OF ADDITIONAL PILE DRIVEN TO INCREASE THE CAPACITY OF SUPPORTING LOADS ON VERTICAL PILES   3
what"s the cement, sand, aggregate(consumption) quantity for 10 cm thick roof slab (1:2:4)   3
sir tell me what are the rules to find out the cut length? and what is the deduction in dia to be made ?   2
how to calculate the steel for rcc slab? plz tell me the formula for calculating the steel? AG-Technologies 28
As a site engineer what do you check in foundation before concreting   3
how many 1st class bricks in 1cu feet? L&T 15
what cement consumction plaster 15mm think per sqmt 1:3&1:6 how much kg.   3
Whr is use tierod???what is standard size of it Orbit-Corporation 2
What is the maximum distance between the stirrups?   11
plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work (1sqM)? Sobha-Developers 7
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com