Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3076)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3289)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13331)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2363)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (416)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (79)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (163)
 Instrumentation interview questions  Instrumentation Interview Questions (2381)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (106)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (43)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (77)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1196)
Question
what,s the clear cover of beam,slab,column,lintel and 
foundation?
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
clear cover for slab-15mm
for beam- 25mm
for column- 40mm
for foundation- 40-60mm
for lintel- 20mm
 
Is This Answer Correct ?    187 Yes 4 No
Ravikumar Patil
 
Answer
# 2
Clear cover depends upon exposure condition it varies
condtion to condition Generally it is For Beam 25mm,Slab
15mm, Column 40mm and Foundation 50 mm
 
Is This Answer Correct ?    80 Yes 2 No
Jayshankar Dwivedi
 
 
 
Answer
# 3
clear cover for slab-15mm
for beam- 25mm
for column- 40mm
for foundation- 50mm
for lintel- 20mm
 
Is This Answer Correct ?    48 Yes 6 No
Maharshi
 
Answer
# 4
clear cover beam is 30mm and slab is 20mm and column is
40mm and lintel is 15mm
 
Is This Answer Correct ?    77 Yes 46 No
Durairajan
 
Answer
# 5
it depends upon the exposure condition and fire resistance.
but normally it is taken as follows,

slab =20mm
beam =25mm
column =40mm
footing=50mm
 
Is This Answer Correct ?    20 Yes 9 No
Mahendra
 
Answer
# 6
Clear Cover for
beam,column 1.5"
slab 3/4"
foundation 2.5"-3"
 
Is This Answer Correct ?    14 Yes 7 No
Rasel Cee
 
Answer
# 7
concrete Nominal clear cover details for some structures
1.Slab 15mm
2.Column 40mm
3.Beam 30mm
4.Footing 40mm
Clear cover is also depend on the corrosion free and fire resisting for reinforcements.
 
Is This Answer Correct ?    11 Yes 8 No
Vasanth.j
 
Answer
# 8
Above somebody says, that it depends upon exposure conditions at currently,it's correct
but normally for
slab=20mm
column=50mm
beam=40mm
lintel=15mm
 
Is This Answer Correct ?    1 Yes 0 No
G. Sabarish
 
Answer
# 9
clear cover depends upon the durability requirements and fire resistance...but in generally it may b taken as follows
footing-40mm
column-40mm
wall-35mm
beam-30mm
slab-15mm
lintel-20mm
 
Is This Answer Correct ?    10 Yes 15 No
Ange.smi
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
What does 'M' stands for in M24 bolt ? RITES 1
how many meters for brad gauge?   5
HOW TO CALCULATE REINFORCMENT IN STAIRCASE CRANKED BEAM L&T 1
how to calculate stair case landing slab bottom shuttering marking,angle of stair case? top landing length-1250mm treads length-2700mm(9X300mm) rise length-1500mm(10X150mm top landing level +1.5m lvl bottom level-0.00m lvl Thermax 2
How can effect the Floor tiles if water absorption value is higher than 0.5%?   1
What is the ring size of column 600x400 (8mm dia ring) ? Simplex 11
what is superelevation?   3
What is meant by End contractions   1
what"s the formula to calculate the water for M15 grade concrete?   3
How Mney Layers in 8mm plywood Orbit-Corporation 2
25. Are you willing to work overtime?   5
why the compressive strength of concrete is calculated only after 28 days.why not after 25, 26,27 days..   6
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com