ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
info       Did you received any Funny E-Mails from your Friends and like to share with rest of our friends? Yeah!! you can post that stuff   HERE
Google
   
 
Categories  >>  Engineering  >>  Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions
 Electrical Engineering interview questions  Electrical Engineering Interview Questions
 Electronics Communications interview questions  Electronics Communications Interview Questions
 Chemical Engineering interview questions  Chemical Engineering Interview Questions
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions
 Bio Engineering interview questions  Bio Engineering Interview Questions
 Metallurgy interview questions  Metallurgy Interview Questions
 Industrial Engineering interview questions  Industrial Engineering Interview Questions
 Instrumentation interview questions  Instrumentation Interview Questions
 Automobile Engineering interview questions  Automobile Engineering Interview Questions
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions
 Marine Engineering interview questions  Marine Engineering Interview Questions
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions
 Engineering AllOther interview questions  Engineering AllOther Interview Questions
Question
Laboratory experiments conducted in Mumbai on a particular 
mix showed a
strength of 33 MP a for a fully matured concrete. Find 
whether formworm
can be removed for an identical concrete placed at Jammu at 
the age of 15
days when the average temperature is 60C. The stripping 
stress in concrete
 Question Submitted By :: Manohar Cherala
I also faced this Question!!     Rank Answer Posted By  
 
  Re: Laboratory experiments conducted in Mumbai on a particular mix showed a strength of 33 MP a for a fully matured concrete. Find whether formworm can be removed for an identical concrete placed at Jammu at the age of 15 days when the average temperature is 60C. The stripping stress in concrete
Answer
# 1
First thing the question is not completely and correctely
typed. The stripping stress in concrete in missing and also
how 60 deg temp will be possible in Jammu & Kashmir.
Let us connsider the Stripping stress of concrete as 25 Mpa
and average temp is 6 deg.

Now,

Maturity = Submission (time x temp)
= 15 x 24 x [6 - (11)]
= 6120 deg CH

Plowman's Constant given as A = 21 and B = 61


Se/S 15 = A + B Log10 [ M /1000]

Percentage of strength = 21 + 61 log(6120/1000)
= 68.99

The strength of Concrete at 15 days = 33 x (68.99/100)

= 22.76 Mpa

Since the strength of concrete is less than the stress


 
Is This Answer Correct ?    0 Yes 0 No
Buntychandwani
[HCC]
 
  Re: Laboratory experiments conducted in Mumbai on a particular mix showed a strength of 33 MP a for a fully matured concrete. Find whether formworm can be removed for an identical concrete placed at Jammu at the age of 15 days when the average temperature is 60C. The stripping stress in concrete
Answer
# 2
First thing the question is not completely and correctely
typed. The stripping stress in concrete in missing and also
how 60 deg temp will be possible in Jammu & Kashmir.
Let us connsider the Stripping stress of concrete as 25 Mpa
and average temp is 6 deg.

Now,

Maturity = Submission (time x temp)
= 15 x 24 x [6 - (11)]
= 6120 deg CH

Plowman's Constant given as A = 21 and B = 61


Se/S 15 = A + B Log10 [ M /1000]

Percentage of strength = 21 + 61 log(6120/1000)
= 68.99

The strength of Concrete at 15 days = 33 x (68.99/100)

= 22.76 Mpa

Since the strength of concrete is less than the stress to
which it is likely to be subjectd while stripping the
formwork, the concrete may fail. Therefore, the formwork
cannot be removed at 15 days time.
 
Is This Answer Correct ?    0 Yes 1 No
Buntychandwani
[HCC]
 
 
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
what is the load acting on the sides of the water tank  2
what is a civil enggineer ? ICICI3
why 1.25 factor is to be multiplied to cylindrical strength of concrete while getting the equvalent cubical strength of concrete?  9
why main steel is to be reinforced in shorter direction in case of slab? Kirloskar8
1m3 3/4 inch course agreegate concrete is which m3 of agreegate ?  3
Hi, Please tell me the ISI specification for the duration of concrete to achieve full strength of concrete. Is it 28days? UPSC5
1:5:10 isme 1 kya h 5 kya h 10 kya h  7
What is the exact meaning for under & over reinforced beams & when they have to used.. L&T6
how many types of hydraulic coefficints and their values  2
How do we calculate the weight of aggregates, sand and cement M 25 design mixfor 1 cum  1
how to calculate stirrups length for circular column  3
what is the density of compacted earth and jamuna sand  2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Help  |  Site Map 1  |  Articles  |  Site Map  |   Site Map  |  Contact Us interview questions urls   External Links 
   
Copyright © 2012  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  Forum9.com   ::  KalAajKal.com