ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3120)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3299)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13431)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2385)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (420)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (165)
 Instrumentation interview questions  Instrumentation Interview Questions (2398)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (107)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (79)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1203)
Question
What is the proportion of cement agg. and sand for M20,M25 
and M30?
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
M20 - 1(Cement):1(1/2)(Fine aggregate):3(Coarse aggregate)
M25 - 1(Cement):1(Fine aggregate):2 (Coarse aggregate)
 
Is This Answer Correct ?    67 Yes 14 No
G.karthikeyan
 
Answer
# 2
mM20 : 1:1.5: 3

M25 : is a design mix. & the proportion can be obtained
only on the basis of materials required & only in the lab.
 
Is This Answer Correct ?    42 Yes 8 No
Shabarish
 
 
 
Answer
# 3
The mix proportions for M20 & M25 both, shall be designed
by laboratory trials and designed according to BIS 10262,
383 & 456 or SP 23. The ratio 1:1.5:3 was given earlier in
IS 456 but IS 456 (2000) does not recommend volumetric
batch for even M20 and hence both should be designed as per
requirement, i.e. it depends on the type of cement,
gradation of aggregates,workability required and
importantly the water cement ratio.
 
Is This Answer Correct ?    20 Yes 2 No
Bhavna Tripathi
 
Answer
# 4
M20 1:1.5:3
M25 1:1:2
M30 will depend upon the mix design
 
Is This Answer Correct ?    19 Yes 1 No
Ashish
 
Answer
# 5
M10 manual mix, proportion is 1:3:6(C:FA:CA)
M15 manual mix, proportion is 1:2:4

> M15 are design Mix, and proportion on Weight basis (not by
volume basis) depend upon grade/type of cement, type of fine
aggregate and Coarse aggregate

However for the estimate purpose the cement can be calculated
For M15 (1:2:4) cement is 6.37 bags/Cum
M20(1:1.5:3) Cement -8.09 bags/Cum
M25 (1:1:2)cement -12.2 bags/Cum
 
Is This Answer Correct ?    22 Yes 4 No
Nimmakayala
 
Answer
# 6
M20 1:1 1/2:3
M25 1:1:2
M30 Proportion not specified its depending upon mix design'
 
Is This Answer Correct ?    16 Yes 4 No
Tiru
 
Answer
# 7
M5,M7.5,M10,M15,M20 -nominal mixes(by wt or by volume)
M25-both nominal and design mix
M30,M35,M40-design mixes(mixes designed specially in lab)
 
Is This Answer Correct ?    2 Yes 0 No
Sobhanbabu
 
Answer
# 8
concrete is designed by Job Mix Formulae, not just by
taking some standard values
 
Is This Answer Correct ?    1 Yes 3 No
Aditya Richie
 
Answer
# 9
M 15 - 1:2:4 , M20 - 1:1.5"3 , M30 - 1:1:2 
Is This Answer Correct ?    2 Yes 7 No
Muthazhagi
 
Answer
# 10
M20 1:2:4
M25 1:1.5:3
M30 1:1:2
 
Is This Answer Correct ?    2 Yes 21 No
Deepak Kumar
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
what is diffence in grade 43 & 53 of cement? NICE 3
hai,i completed my b.tech civil.Recently i wrote the appsc exam for managers water supply engg.I want answers for general studies and civil engg paper2.If any body know or written that exam send to my mail id is ruksana.sk08@gmail.com. APPSC 3
how do measure the safe bearing capacity of soil? what is the compresive strength for concret?(max.&min.)   1
calculation of quantities of cement and sand in 1cum mortar with 1:6 ratio Oasis 3
which beam has more strength rectangular or circular   3
CALCULATE QUANTITY OF RCC COLUMN NBCC 2
in staad which are the point is to be checked for not fail of structure   1
why red bricks used for brickbat coba   1
what is the detention period for oxidation ponds   2
what is the minimum and maximum water cement ratio   5
the capacity of water tank in liters if the diameter is 3m, and maximum height of water level as 1m. l&t 11
Please can anybody let me know how to calculate cement, sand & aggregete content for one meter cube of concrete. please if possible provide calculations for cement in no. of bags, sand & aggregate in cu.mt. Thanks.   2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com