1. insulation resistance 2.ratio test 3.magnetising current
4. magnetising balance
Is This Answer Correct ? | 1 Yes | 0 No |
what is power factor
Why should we hire you over the others waiting to be interview?
How to design harmonic filter at the project stage without nowing the harmonics levels
Advantages of using generator circuit breaker (GCB) scheme in a power station ?
what is megar testing
I need tnpsc AE Electrical question papers
2 Answers TNPSC Tamil Nadu Public Service Commission,
1)What are the proccedure of initial charge of 100AH lead Acid battery bank 2)whether discharge test is reqd ? if it is rqd why, how 3)what are the discharge critieria (volt/cell or sp.gravity/cell
what is the purpose of ignitor in lighting fixer
how can maintaince the acb contactor moveing and fixing kit
how to introduce yourself
A IS TWICE AS GOOD A WORKMAN AS B AND TOGETHER THEY FINISH A PIECE OF WORK IN 14 DAYS.THE NUMBER OF DAYS TAKEN BY A ALONE TO FINISH THE WORK IS 1.11 2.21 3.28 4.42
If the rated speed of a d.c. Shunt motor is1440 r.p.m, which method of speed control would you suggested to obtain a speed of 1500 r.p.m?