ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Business Management >> IT Management
 
 


 

 
 Business Administration interview questions  Business Administration Interview Questions (411)
 Marketing Sales interview questions  Marketing Sales Interview Questions (871)
 Finance interview questions  Finance Interview Questions (1024)
 Human Resources interview questions  Human Resources Interview Questions (699)
 Personnel Management interview questions  Personnel Management Interview Questions (11)
 Hotel Management interview questions  Hotel Management Interview Questions (17)
 Industrial Management interview questions  Industrial Management Interview Questions (58)
 Infrastructure Management interview questions  Infrastructure Management Interview Questions (12)
 IT Management interview questions  IT Management Interview Questions (87)
 Non Technical interview questions  Non Technical Interview Questions (67)
 Business Management AllOther interview questions  Business Management AllOther Interview Questions (363)
Question
How do you determine realistic schedules for the project?
 Question Submitted By :: Great_gramo
I also faced this Question!!     Rank Answer Posted By  
 
  Re: How do you determine realistic schedules for the project?
Answer
# 1
According to Verzuh, a realistic schedule:
-Includes a detailed knowledge of the work to be done
-Has task sequences in the correct order
-Accounts for external constraints beyond the control of
the team
-Can be accomplished on time, given the availability of
skilled people and enough equipment

There are steps to follow to create realistic project plan.
Step one: Create a work breakdown structure
Step two: Identify task relationships (Network
Diagrams/PERT Charts)
Step three: Estimate work packages
Step four: Calculate an initial schedule
Calculating the schedule is a three-step process; forward
pass, backward pass, and calculate float. Forward pass
helps you determine the early start (ES) and early finish
(EF) for each task. Backward pass determines the late start
and late finish dates. Calculate float means flexibility in
the schedule and calculated buy subtracting early start
from late start. Critical path has no float, so it should
begin and finish on time.
Step five: Assign and level resources
Resources mean the people, equipment, and the materials.
And the leveling follows a four-step process:
1. Forecast the resource requirements throughout the
project for the initial schedule.
2. Identify the resource peaks.
3. At each peak, delay noncritical tasks within their float.
4. To eliminate the remaining peaks, reevaluate the work
package estimates.
This detail and realistic schedule may not solve all the
problems but wil provide a tool set for solving many of
them.
 
Is This Answer Correct ?    59 Yes 7 No
Hyejung Kwon
 

 
 
 
Other IT Management Interview Questions
 
  Question Asked @ Answers
 
In SAP SD , HOw to remove the materail block ?   1
What is the difference between product based and service based IT companies? ABC 2
what are charateristics of business analsyt   1
Which managerial function gives attention to influencing and motivating employees to improve performance and achieve corporate objectives?   1
why do you join mba in IT sector?   3
what is the difference between oracle ERP products and SAP ERP products?   1
Write a C Program to declare an array for 2 0 floats. Accept the values from the user sort the two arrays in descending order. Merge the two arrays into a new array and display the new array. Symbiosis 1
What motivates you? How do you motivate others?   3
in my office to access data fast i replaced 8 port hub with 8 port dlink switch my network connectivity is gone all the led keep blinking do you i have to change cabeling or change the switch   1
what is the difference between BI and pervasive BI? NIIT 1
How do you monitor risks to the project and mitigate them? Safeway 1
what is the difference between database software, middleware and enterprise application software SAP-Labs 2
 
For more IT Management Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com