ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Software >> Testing >> Test Documents Reporting
 
 


 

 
 Automation Testing interview questions  Automation Testing Interview Questions (5200)
 Manual Testing interview questions  Manual Testing Interview Questions (6477)
 QA Concepts interview questions  QA Concepts Interview Questions (655)
 Mobile Testing interview questions  Mobile Testing Interview Questions (113)
 Test Cases interview questions  Test Cases Interview Questions (469)
 Test Documents Reporting interview questions  Test Documents Reporting Interview Questions (58)
 Testing AllOther interview questions  Testing AllOther Interview Questions (609)
Question
How do we prepare weekly and monthly status-report as QA?
 Question Submitted By :: Test-Documents-Reporting
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
Weekly Status Reports:

Overall activities Status RED/AMBER/GREEN

1. Title
2. Activities Planned this week:

3. Activities Completed this week:
- Sr. No
- Description
- Planned Start Date
- Actual Start Date
- Planned End Date
- Actual End Date
- % Compled
- Status
4. Activities in Progress
- Sr. No
- Description
- Planned Start Date
- Actual Start Date
- Planned End Date
- Actual End Date
- % Compled
- Status
5.Activities planned next week:

6. Defect Matrix
- No of defects
i) New
ii) Open
iii) Closed
iv) Deferred
v) Rejected

7. Risks and Issues if any


Monthly Status report is a high level report
Overall activities Status RED/AMBER/GREEN
1. Activities Planned
2. Activities Completed
3. Activities In Progress
4. Activities Planned Next
5. Risks and Issues
 
Is This Answer Correct ?    19 Yes 5 No
Rahul
 
Answer
# 2
Rahul answer is good !!! 
Is This Answer Correct ?    5 Yes 1 No
John
 
 
 
Answer
# 3
Do you have any calculation for defects? Defect per
day/Total no. of defect in a week???
 
Is This Answer Correct ?    3 Yes 0 No
Srikumaran
 
Answer
# 4
hi rahul
can explain with example it is useful to me........pls
thnks
 
Is This Answer Correct ?    2 Yes 4 No
Sasi
 

 
 
 
Other Test Documents Reporting Interview Questions
 
  Question Asked @ Answers
 
Need information on Documentum4.3, any websites. What is this Documentum,how to access,features and benefits. ASAP Thx. Cap-Gemini 1
what are the fields in Bug Report RMSI 2
What do you mean to CAPA?   3
Hi Friends, Can any one tell me how the Risks for the basic web page testing in the Test Plan, as i am writting my first test plan. It will be greatfull if any one answer me as soon as possible   3
What is Defect/Bug/Error Life Cycle? Covansys 10
how many levels of test execution will you follow and describe them?   7
After asking the defect life cycle, if you think it is not a valid defect, what you will do, whether you will store in any document for future reviews,if yes, what is that document, where you will save that document? or just reject it and close it?   4
What are the contents of Test Plan?   4
what is the meaning of the test strategy and what it consists?   6
can you plz tell me the all documents to be completed by a manual tester? InfoStep 8
what are the fields in traceablity matixes. HCL 7
differentiate test strategy and test plan?   5
 
For more Test Documents Reporting Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com