Answer / vedha_sathya

test plan prepares in each and every phage in In vlidation
phase that is right hand side

Is This Answer Correct ?    3 Yes 1 No

When test plan will be prepared in v-model?..

Answer / jay

designing phase

Is This Answer Correct ?    2 Yes 0 No

When test plan will be prepared in v-model?..

Answer / guest

requirements phase it self

Is This Answer Correct ?    2 Yes 1 No

When test plan will be prepared in v-model?..

Answer / saff

hi all plz correct meif i am wrong

a/c to my knowledge just acquired

test plan is written in the beginning itself that is after
we get requirmetns

this will be a documented and as we get the new info from
development we will be updating the info in the test plan


why because if we dont do test plan first ,how can we tell
how much time it will take for testing what ever phase we r
testing

Is This Answer Correct ?    1 Yes 0 No

When test plan will be prepared in v-model?..

Answer / karthik.g

The test plan will be prepared in various stages in a V
Model.

The UAT Test plan will be prepared at the requirement
analysis phase as one of our friend has said and the System
test plan will be prepared during the High Level Design
Phase. The integration test plan during the Low Level
Design phase.

Is This Answer Correct ?    1 Yes 1 No

When test plan will be prepared in v-model?..

Answer / vishnu

a rough test plan at requirements phase
testplan at hld phase
according to that every activity will be done.
like templates used inside
inscope and outscope
milestones
terminology
risks and mitigation plans
and so on.
so plan is there from the beginning.

Is This Answer Correct ?    0 Yes 0 No

When test plan will be prepared in v-model?..

Answer / g

1> System test plan in requirement analysis phase;
2> Integration test plan in High level Design phase;
3> Module test plan in Low Level Design phase;

Is This Answer Correct ?    1 Yes 2 No

Post New Answer

More Manual Testing Interview Questions

can any body explain about BVA and ECP briefly?

3 Answers  


Explain Test Plan with example? Explain following in the test plan with examples What is being tested? What are pass/fail criteria? When will each test occur? What Hardware & Software environment is required? What features must be tested? What features will not be tested? What are the responsibilities of individuals & organisation in the project?

0 Answers  


this is a question asked by an interviewer..."why have u choose the testing field"

2 Answers  


What is a defect age?

0 Answers  


Write down ten test cases for below scenario: Increase the day by 1 and date format should be mm/dd/yyyy Conditions are : date should not be greater then 31 and date<1 month should not be greater then 12 and month<1 year should not be greater then 10000 and year<1 Thanks in advance

0 Answers   Wipro,






can any one please tell me the types of defects in s/w testing

3 Answers   Symphony,


On Registration Form, if some fields are not mandatory to fill then those fields can accept any invalid input. OR there may have some validation. E.g. Email id field - Not mandatory to fill. If user enter Email id = 453454 should it accept?

1 Answers  


What is Software Testing? Objectives of Testing?

3 Answers   Satyam,


1. what is a difference between test plan and test strategy?2.What is the test plan is different from the test strategy? then how?

2 Answers  


What is Load Testing and Stress Testing explain it with examples

6 Answers   HSBC, TCS,


what are the advantages of manual and automation testing ? and which one would u term as efficent testing and effective testing ?pls do reply thankx in advance its urgent

4 Answers   HCL,


If I want to check compability of software in a MAC OS then which steps shold I follow?

0 Answers  


Categories