ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Software >> Testing >> Manual Testing
 
 


 

 
 Automation Testing interview questions  Automation Testing Interview Questions (5206)
 Manual Testing interview questions  Manual Testing Interview Questions (6496)
 QA Concepts interview questions  QA Concepts Interview Questions (656)
 Mobile Testing interview questions  Mobile Testing Interview Questions (115)
 Test Cases interview questions  Test Cases Interview Questions (469)
 Test Documents Reporting interview questions  Test Documents Reporting Interview Questions (58)
 Testing AllOther interview questions  Testing AllOther Interview Questions (609)
Question
Phases of Software Testing Life Cycle?
 Question Submitted By :: Manual-Testing
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
The phases of Software Life cycle model is follows :

1. Effort Estimations
2. Project Initiations
3. System Study (Analyse the System Requirement
Specifications)
4. Test Plan.
5. Test Case Generation.
6. Test Case Execution
a. Manual
b. Automation
7. Defect Report
8. Regression Testing
9. Analysis
10.Defect Summary Report.

if any query plz send me mail ....
my mail Id : pradhan.sunil@gmail.com
 
Is This Answer Correct ?    15 Yes 4 No
Sunil Ranjan Pradhan
 
Answer
# 2
Requirements analysis: Testing should begin in the
requirements phase of the software development life cycle.
During the design phase, testers work with developers in
determining what aspects of a design are testable and with
what parameters those tests work.
Test planning: Test strategy, test plan, testbed creation.
A lot of activities will be carried out during testing, so
that a plan is needed.
Test development: Test procedures, test scenarios, test
cases, test datasets, test scripts to use in testing
software.
Test execution: Testers execute the software based on the
plans and tests and report any errors found to the
development team.
Test reporting: Once testing is completed, testers generate
metrics and make final reports on their test effort and
whether or not the software tested is ready for release.
Test result analysis: Or Defect Analysis, is done by the
development team usually along with the client, in order to
decide what defects should be treated, fixed, rejected
(i.e. found software working properly) or deferred to be
dealt with at a later time.
Retesting of resolved defects: Once a defect has been dealt
with by the development team, it is retested by the testing
team.
Regression testing: It is common to have a small test
program built of a subset of tests, for each integration of
new, modified or fixed software, in order to ensure that
the latest delivery has not ruined anything, and that the
software product as a whole is still working correctly.
Test Closure: Once the test meets the exit criteria, the
activities such as capturing the key outputs, lessons
learned, results, logs, documents related to the project
are archived and used as a reference for future projects.
 
Is This Answer Correct ?    10 Yes 4 No
Abhishek
 
 
 
Answer
# 3
These are the phases of STLC

1.Requirements
2.Use Case Document
3.Test Plan
4.Test Case
5.Test Case execution
6.Report Analysis
7.Bug Analysis
8.Bug Reporting

byee friends
Rajendra
rajendra_penumalli@yahoo.com
 
Is This Answer Correct ?    21 Yes 16 No
Rajendra
 
Answer
# 4
1. Test plan
2. Test Design
3. Test execution
4. Test log
5. Defects
6. Report generation
 
Is This Answer Correct ?    6 Yes 4 No
Bharani.p
 
Answer
# 5
1. Requirement gathering
2. Planning
3. Design
4. Coding
5. Testing
6. Deployment
 
Is This Answer Correct ?    10 Yes 9 No
Suriya
 
Answer
# 6
1.Requirement Stage
2.Test Planning
3.Test Analysis
4.Test Design
5.Test Verification and Construction
6.Test Execution
7.Result Analysis
8.Bug Tracking
9.Reporting and Rework
10.Final Testing and Implementation
11.Post Implementation
 
Is This Answer Correct ?    0 Yes 0 No
Deepu
 
Answer
# 7
Test Planning
Test Development
Test Execution
Test Analysis
Bug Tracking
Report Generation
 
Is This Answer Correct ?    3 Yes 5 No
Gaurav
 
Answer
# 8
Requirements (bsd and fsd document)
the test plan document.
Design the Test Cases.
review and approval of test cases
execute the test cases,
find any bugs we post the bugs into Defect Tracking Tool.
re test ok close else re-open
 
Is This Answer Correct ?    10 Yes 13 No
Jagadish
 
Answer
# 9
software testing life cycle is nothing but the procedure
which we will follow during your testing.it contains
certain phasaes they are
1.test strategy
2.test plan
3.test Design
4.test Execution
5.test log
6.defect tracking
 
Is This Answer Correct ?    6 Yes 10 No
Soumya
 
Answer
# 10
Testing process is done as follows:

1. Requirement Analysis
2.Test Planning
3.Test Development
4.Test Execution
5.Test Reporting
6.Retesting the defects(Regression testing)
 
Is This Answer Correct ?    1 Yes 7 No
Ranjitha
 

 
 
 
Other Manual Testing Interview Questions
 
  Question Asked @ Answers
 
When is Ad-hoc Testing done in a project?   4
hi how to test a video files? and what type of test stategy you follow to test a video files?   2
what is mean by end to end testing?   5
what is stub and driver ?explane in brife.,and some example   6
In a Dark Room one Switch Board is there.If u Pressed a Button in Switch Board the Light will 'ON'. Write the Possible test cases?   7
Where will you give the Reproduce option in Bug report? GE 2
Who fixes the bug as Severity and priority ? Access 12
After insert the record in forntend, How will u check the backend by manually? Please explain..   4
How is the communication with the developers for the Unit Testing? CSS 2
What is Traciability Matrix Airbee 10
1.write test cases for bangle 2.what is difference between defect and bug life cycle 3.what are the inputs for writing test cases 4.how to map requirements to test cases 5.where to attached the test cases 6.what is sdlc 7.what are the difference between sanity and smoke testings 8. user accaptance testing types 9.what is the mail module in qc 10.why are u changing ur job Cap-Gemini 2
Difference between Test Plan & Test Strategy?   6
 
For more Manual Testing Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com