Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3069)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3285)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13310)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2356)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (414)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (79)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (163)
 Instrumentation interview questions  Instrumentation Interview Questions (2372)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (106)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (43)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (75)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1194)
Question
what are IS code for 
M20, 25, etc
 Question Submitted By :: Guest
I also faced this Question!!     Rank Answer Posted By  
 
  Re: what are IS code for M20, 25, etc
Answer
# 1
is 456 2000 
Is This Answer Correct ?    333 Yes 30 No
Kaushik
 
  Re: what are IS code for M20, 25, etc
Answer
# 2
Code of practise for plane nad reinforced concrete : IS 456-
2000.
 
Is This Answer Correct ?    244 Yes 23 No
Mishijoshi
 
 
 
  Re: what are IS code for M20, 25, etc
Answer
# 3
Code for M20 and 25 are IS 456-2000 for concrete mix design
and element design and also IS-516 will be required for
testing of concrete.
 
Is This Answer Correct ?    148 Yes 38 No
Rajkumar
 
  Re: what are IS code for M20, 25, etc
Answer
# 4
1:1.5:3, 
Is This Answer Correct ?    71 Yes 107 No
Mari2selvan@yahoo.co.in
[L&d]
 
  Re: what are IS code for M20, 25, etc
Answer
# 5
THE IS CODE FOR M20 & M25 IS ...IS 456:2000.
THIS CODE GIVES THE PROCEDURE OF MIX DESIGN.
 
Is This Answer Correct ?    112 Yes 25 No
Joseph Ravi Kiran
 
  Re: what are IS code for M20, 25, etc
Answer
# 6
IS CODE FOR M20 , M25 , ETC IS IS 456:2000 
Is This Answer Correct ?    97 Yes 18 No
Jaydeep Banerjee
 
  Re: what are IS code for M20, 25, etc
Answer
# 7
GO AND SEE IS CODE 10262 FOR ALL MIX DESIGN 
Is This Answer Correct ?    67 Yes 28 No
Faraheem
 
  Re: what are IS code for M20, 25, etc
Answer
# 8
is 456 2000 
Is This Answer Correct ?    61 Yes 13 No
Ramana
 
  Re: what are IS code for M20, 25, etc
Answer
# 9
IS 456-2000 
Is This Answer Correct ?    57 Yes 9 No
Narayana
 
  Re: what are IS code for M20, 25, etc
Answer
# 10
456:2000 
Is This Answer Correct ?    46 Yes 13 No
Furqan Ansari
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
WHAT IS THE DIFFERENCE BETWEEN "WORKING STRESS METHOD" AND "LIMIT STATE METHOD"? TCE 11
How to calculate the thickness of the rcc slab?ll u pls tell the formula?   2
In pile foundation which kind of action are take place?   2
What is the volume of sand in per cubic meter if we have a design mix of concrete is 1:2:4 (by volume).   1
wheather Micro silica/silica fumes is an ad-mixture or accelerator. Coastal-Projects 4
NP3 CLASS HUME RCC PIPE   1
why cutting length in design of beam is rounded more for -r/f & less for for +r/f   1
For G+4 storied building having 76000 sft per each floor, can you prepare schedule in such a way that structure should be completed with in 41/2 months and finishing be completed with in 51/2 months?   1
Method of findingthe dry ingredient quantity of 1 m3 concrete. L&T 14
What"s the brick size we use in construction?1.190x90x90 2.230x100x75 Which one "s correct? Jaypee 12
What is the Density of Steel & Conccrete   4
How to findout safe bearing capacity after stabilization of soil by method of the confinde method.   3
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.