ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
tip       Ask Questions on ANYTHING, that arise in your Daily Life at     FORUM9.COM
Google
   
 
Categories  >>  Engineering  >>  Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions
 Electrical Engineering interview questions  Electrical Engineering Interview Questions
 Electronics Communications interview questions  Electronics Communications Interview Questions
 Chemical Engineering interview questions  Chemical Engineering Interview Questions
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions
 Bio Engineering interview questions  Bio Engineering Interview Questions
 Metallurgy interview questions  Metallurgy Interview Questions
 Industrial Engineering interview questions  Industrial Engineering Interview Questions
 Instrumentation interview questions  Instrumentation Interview Questions
 Automobile Engineering interview questions  Automobile Engineering Interview Questions
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions
 Marine Engineering interview questions  Marine Engineering Interview Questions
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions
 Engineering AllOther interview questions  Engineering AllOther Interview Questions
Question
what is right time of slab DE shattering and beam boo tam.
 Question Submitted By :: Harendrarana45
I also faced this Question!!     Rank Answer Posted By  
 
  Re: what is right time of slab DE shattering and beam boo tam.
Answer
# 1
It depends up on span of the beam normally after 7 days we can remove shuttering and support with props. 
Is This Answer Correct ?    21 Yes 3 No
Map
 
  Re: what is right time of slab DE shattering and beam boo tam.
Answer
# 2
The time of slab deshutting after getting 67% strength at 4 or 7 days same for beam bottom and it also depend of span of beam. 
Is This Answer Correct ?    19 Yes 2 No
Azam
 
 
 
  Re: what is right time of slab DE shattering and beam boo tam.
Answer
# 3
DE shattering can be done for slab bottom after 3days and Beam bottom after 7 day,but immediately props to be refixed. 
Is This Answer Correct ?    2 Yes 2 No
Md Nezam
 
  Re: what is right time of slab DE shattering and beam boo tam.
Answer
# 4
slab de shetting 2 day 
Is This Answer Correct ?    0 Yes 2 No
R.ranjith Kumar
 
  Re: what is right time of slab DE shattering and beam boo tam.
Answer
# 5
as per IS 456 beam bottome should be remove after 14 days.
concrete strength is more than 70%. if span is more than 11
mt then its remove after 21 days.
 
Is This Answer Correct ?    7 Yes 1 No
Ronak Shah
 
  Re: what is right time of slab DE shattering and beam boo tam.
Answer
# 6
Beam Sides can be allowed to be removed on the next day of
casting.
Bottoms should be allowed only after 7 days of casting.
This is practical answer on site otherwise contractors will
run away.
 
Is This Answer Correct ?    1 Yes 0 No
Mitesh Patel
 
  Re: what is right time of slab DE shattering and beam boo tam.
Answer
# 7
span length below 4.5m 7 days
span length over 4.5m 14days
 
Is This Answer Correct ?    0 Yes 0 No
Ananth
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
what is the difference between ribbed steel & tor Steel ?  1
What do you mean by "M-30"? CDS5
what are the criteria for choosing the span for the bridge (highway bridge)  4
What is different type of bills?  1
Drar the reinforcement detailing of Internal Hinge ? RITES1
what is the least-count of plane- table,dumpy,theodolite,compass,tachometer?  2
how much length will be deducted when a reinforcement steel bending?  3
one MT of steel for using how much binding wire required?  5
what is a exact size of a cube? Green-Concretex5
what is the main difference b/w compaction and consolidation KCP2
what is the ratio of young's modulus of elasticity for a mild steel specimen in tension and compression? CCCL6
What is approximate % of wastage considered for Marble and vitrified tiling works (flooring)?  1
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Help  |  Site Map 1  |  Articles  |  Site Map  |   Site Map  |  Contact Us interview questions urls   External Links 
   
Copyright © 2012  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  Forum9.com   ::  KalAajKal.com