ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3112)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3298)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13412)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2382)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (420)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (165)
 Instrumentation interview questions  Instrumentation Interview Questions (2392)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (106)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (78)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1202)
Question
How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
bricks 500 nos
cement 1.88 bags
sand .266 cum
 
Is This Answer Correct ?    69 Yes 34 No
Arunothayan Umakanthan
 
Answer
# 2
500bricks 
Is This Answer Correct ?    33 Yes 22 No
Guest
 
 
 
Answer
# 3
brick = 480 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .255 for one cum
 
Is This Answer Correct ?    16 Yes 5 No
Farvaris Kumar
 
Answer
# 4
1# Brick calculation
size of brick eg:- 200mmx10mmx10mm
1/.20x0.1x0.1 =500nos/cum.

2#Cement :- 0.3/1+5=0.05cum
:- 0.05x28.8=1.44bags.

3#Sand :- 5x0.05=0.25cum
 
Is This Answer Correct ?    29 Yes 20 No
Saif Raza
 
Answer
# 5
Bricks = 500 no.
cement = 1.762
sand = 0.306 cum
 
Is This Answer Correct ?    4 Yes 2 No
Neelesh Chouhan
 
Answer
# 6
Volume of Dry Mortar = 35% of volume of Brickwork

Volume of Mortar required = 0.35 X 1 = 0.35 cu.m.

Cement required = 1/6 X 0.35 = 0.058 cu.m. = 1.67 Bags

Sand required = 5/6 X 0.35 = 0.292 cu.m.

Bricks required = 500 Nos.
 
Is This Answer Correct ?    23 Yes 23 No
Mohammed Aijaz Hussain
 
Answer
# 7
Bricks=1/volume of 1 brick

1/.23*.115*.075=504 Nos of Bricks.
But Pricitaly=475 to 485 Nos of bricks(kyoki fat layer not proper 10 0r 12mm).

Sand&Cement =100 cum B/work in 30 cum sand,
Than
cement ratio=1:5
.3/1+5=.05cum dry mortar
(1beg cement volume=(1/28.8)=.0347
Than Cement=.05/.0347=1.44 Bags
Sand =.05*5=.25cum.
 
Is This Answer Correct ?    0 Yes 0 No
Vipin Kumar
 
Answer
# 8
brick = 476 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .250 for one cum
 
Is This Answer Correct ?    1 Yes 2 No
Gulshan Vashisht From Hassanpu
 
Answer
# 9
Bricks = 500 no.
cement = 1.762 beg
sand = 1.836 cum
 
Is This Answer Correct ?    2 Yes 3 No
Neelesh Chouhan
 
Answer
# 10
brick 500
cement 1.6 bags
sand 0301 m3
 
Is This Answer Correct ?    5 Yes 10 No
Brajesh Rai
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
why steel is used in r.c.c why steel is used in r.c.c   4
FULL FROM OF ACC Tcs 1
What is meaning of M25 grade SMC 3
what is difference between long column and short column?   6
say the propotions of different concrete mix desidn(M20 M15 M25 M25 M30)   3
How to calculate cement and sand quantities in cement mortar As 1:1,1:2,1:4,1:6 ? Simplex 15
what is the out turn of one masson in plastering, masonary work in 8 hours, with limited healper? what is the out turn of corpender in form work? wood work? in 8 hour with limited healper? what is the out turn of bar bendarin 8 hour with limited healper for slabs, beams, coloumn?   2
what is tensile strength?   1
which is the cheapest type of temporary flooring(say for using 6 months on)?   1
what is 43 & 53 in cement Simplex 9
density of flyash   2
how you calculate the qty. of cement ,sand,aggregate from proportion 1:2:4 M15   4
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com