ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3157)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3309)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13489)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2396)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (424)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (166)
 Instrumentation interview questions  Instrumentation Interview Questions (2409)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (109)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (82)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1207)
Question
How to calculate the amount of Brick,cement & sand required
for 1 cum of 230mm thick brick work with ratio 1:5 please
give me an answer with detailed step
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
bricks 500 nos
cement 1.88 bags
sand .266 cum
 
Is This Answer Correct ?    76 Yes 36 No
Arunothayan Umakanthan
 
Answer
# 2
1# Brick calculation
size of brick eg:- 200mmx10mmx10mm
1/.20x0.1x0.1 =500nos/cum.

2#Cement :- 0.3/1+5=0.05cum
:- 0.05x28.8=1.44bags.

3#Sand :- 5x0.05=0.25cum
 
Is This Answer Correct ?    34 Yes 20 No
Saif Raza
 
 
 
Answer
# 3
500bricks 
Is This Answer Correct ?    33 Yes 22 No
Guest
 
Answer
# 4
brick = 480 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .255 for one cum
 
Is This Answer Correct ?    17 Yes 6 No
Farvaris Kumar
 
Answer
# 5
Bricks = 500 no.
cement = 1.762
sand = 0.306 cum
 
Is This Answer Correct ?    4 Yes 2 No
Neelesh Chouhan
 
Answer
# 6
Bricks=1/volume of 1 brick

1/.23*.115*.075=504 Nos of Bricks.
But Pricitaly=475 to 485 Nos of bricks(kyoki fat layer not proper 10 0r 12mm).

Sand&Cement =100 cum B/work in 30 cum sand,
Than
cement ratio=1:5
.3/1+5=.05cum dry mortar
(1beg cement volume=(1/28.8)=.0347
Than Cement=.05/.0347=1.44 Bags
Sand =.05*5=.25cum.
 
Is This Answer Correct ?    1 Yes 0 No
Vipin Kumar
 
Answer
# 7
Volume of Dry Mortar = 35% of volume of Brickwork

Volume of Mortar required = 0.35 X 1 = 0.35 cu.m.

Cement required = 1/6 X 0.35 = 0.058 cu.m. = 1.67 Bags

Sand required = 5/6 X 0.35 = 0.292 cu.m.

Bricks required = 500 Nos.
 
Is This Answer Correct ?    23 Yes 23 No
Mohammed Aijaz Hussain
 
Answer
# 8
brick = 476 (as pr calculation)
.3= dry volume of brick mortar
cement = .3*28.8/total of ratio(6)
= 1.44 begs in one cum
sand = .3*quantity of sand(5)/total of ratio
= .250 for one cum
 
Is This Answer Correct ?    2 Yes 2 No
Gulshan Vashisht From Hassanpu
 
Answer
# 9
Bricks = 500 no.
cement = 1.762 beg
sand = 1.836 cum
 
Is This Answer Correct ?    3 Yes 4 No
Neelesh Chouhan
 
Answer
# 10
brick 500
cement 1.6 bags
sand 0301 m3
 
Is This Answer Correct ?    7 Yes 11 No
Brajesh Rai
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
18. What is the thing that might make you happy at your work place?   6
Characteristics of a model project are   1
what is the m25 test result 7 days 14 days   3
A person feels comfort when downs a stair because of   2
1 cubicmeter liquid = how much litre   6
What should be percentage of silt content in sand? TCIL 8
what is bending moment?   4
WHY DO WE USE STIRRUPS IN COLUMNS?   12
what is minimum reinforcement required for rcc works NCC 4
Describe why concrete must be compacted after it is poured?   2
hi i am working in a civil Lab .....they asked me to find out the compressive strength of concrete cubes after 7 days of curing....the value of load on CCT machine is 205KN how to convert it to Kg/cm2 ....plzz help me...........   4
explain kn/sqm in detail.   3
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com