ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3072)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3287)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13322)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2362)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (416)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (79)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (163)
 Instrumentation interview questions  Instrumentation Interview Questions (2375)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (106)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (43)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (75)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1195)
Question
how many labour is required for 1cum of concrete?
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
0.36 skilled and 2 unskilled labour is enough form onc cum
concrete
 
Is This Answer Correct ?    2 Yes 0 No
Enayatullah Mahroowal
 
Answer
# 2
3CUM/DAY/ MASON WITH 1 HELPER CAN DO RCC & 5CUM/DAY/MASON WITH 1 HELPER CAN DO PCC..IS NORMAL PRODUCTIVE NORMS OFA A MASON NOW-A-DAYS 
Is This Answer Correct ?    1 Yes 0 No
Sathesh.b.nama
 
 
 
Answer
# 3
Depend by work
area..
 
Is This Answer Correct ?    0 Yes 0 No
Babu
 
Answer
# 4
Around 2 Mason and 1.5 helper per 1 cum concrete 
Is This Answer Correct ?    0 Yes 9 No
Chandu
 
Answer
# 5
1 Mason with 1 helper can do 30MT3 per day 
Is This Answer Correct ?    5 Yes 16 No
Ahmed
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
whether earth to the height of 80cm could be filled in the basement inm place of jamuna sand L&T 5
why does only water ads in concrete? L&T 5
How much steel required in 1 square feet slab?   11
WHAT IS THE PERMISSIBLE LIMIT OF SILT CONTAIN IN SAND FOR RCC WORK? Ambuja 4
WHICH ONE IS THE ECONOMICAL CONSTRUCTION SOLID BLOCK CONSTRUCTION OR BRICK CONSTRUCTION?   4
1 cubicmeter liquid = how much litre   6
how much grade of concrete can be used for different structural element such as slab,beam,column,footing & plinth beams? and type of cement can be used in construction work & also types of cemnt grades L&T 2
what is the density of Coarse Aggregate in 1 cu m of Concrete?   7
polavaram project is situated inwhich place?   7
what is the significance of soundness test in Cement? and how is it done??   1
what will be the difference in compressive test results for a 150 mm cube, a 150 mm cylinder and a 300 mm cube   5
Can anyone tell me the salary and job profile of transportation engineers/transport engineer?   1
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com