ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3010)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3270)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13221)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2348)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (407)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (76)
 Bio Engineering interview questions  Bio Engineering Interview Questions (16)
 Metallurgy interview questions  Metallurgy Interview Questions (79)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (162)
 Instrumentation interview questions  Instrumentation Interview Questions (2317)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (104)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (43)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (73)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1189)
Question
what is steel consumption for high rise building column, 
beam, slab,footing
 Question Submitted By :: Guest
I also faced this Question!!     Rank Answer Posted By  
 
  Re: what is steel consumption for high rise building column, beam, slab,footing
Answer
# 1
Based on experience the Consuption for a Building of 10-15
Storey :
Beams 125-140 Kg per cu.m of Concrete
Slabs 80-100 Kg per cu.m of Concrete
Columns 350-400 kg per cu.m of concrete
Footings100-125 Kg per cu.m
In general for a Eartquake Resistant Str in Zone 3/4 the
steel consumption can vary between 6.5 to 7.5 Kg per
sq.feet of Constructed area
 
Is This Answer Correct ?    20 Yes 3 No
S.k.roy
 
  Re: what is steel consumption for high rise building column, beam, slab,footing
Answer
# 2
Footings generally will have 50 to 80 Kg/Cum. Other
components are fairly accurate
 
Is This Answer Correct ?    4 Yes 2 No
B.sankararaman
 
 
 
  Re: what is steel consumption for high rise building column, beam, slab,footing
Answer
# 3
100 to 120 kg/cum 
Is This Answer Correct ?    1 Yes 3 No
Sachin
 
  Re: what is steel consumption for high rise building column, beam, slab,footing
Answer
# 4
The overall consumption up to 20 stories residential
building is around 5.5 kg per sqft.
 
Is This Answer Correct ?    1 Yes 1 No
Lalit Lone
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
What is logic behind the use of Steel bar insted of gold bar? Rites 9
you are planning to paint a newly fabricated workshop building made of structural steel of 10 tons total mass.you are require to paint 1 cot of primer and 2 coats of top coat.How many liters of primer and top coat you will request   1
Concrete Mix designs for M15,M20,M25,M30 and M35 ATCO 19
How to preparation billing for high rise building? anyhow can give the tips L&T 2
why main steel is to be reinforced in shorter direction in case of slab? Kirloskar 9
what is the lap length on column? state the farmula plz with explaination.   3
what is the name of software for designing of R.C.C.structures   9
in how much square meter of slab we are providing a beam it may be oneway or twoway slab.   1
when does sedimentation occur before filteration, along with it, along with chlorination, after chlorination? NTPC 7
for rcc which condition will u adopt now bscpl 4
why there is no concrete mix of ratio 1:.5:1   2
URGENT: please tell me what's normal drawing scale for residential building and commercial building? Thanks.   5
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com