ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3157)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3309)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13491)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2396)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (424)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (166)
 Instrumentation interview questions  Instrumentation Interview Questions (2409)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (109)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (39)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (82)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1211)
Question
distinguish between under reinforced and over reinforced 
beams?
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
When the maximum stresses in steel and concrete
simultaniously reaches allowable value the section is
called balanced section
when the %of steel in a section is less than that
required for a balanced section it is under reinforced
section
when the %of steel in a section is more than that
required for a balanced section it is over reinforced
section
 
Is This Answer Correct ?    27 Yes 2 No
Subair
 
Answer
# 2
over reinforcement is as per section design I.e Ast1+Ast2>Ast
Ast1+Ast2<Ast it is under reinforced section


conclussion is : Total area of steel is less than the designed one it is under reinforced section
Total area of steel is over than the designed one it is over reinforced section
 
Is This Answer Correct ?    15 Yes 5 No
S.venkatesh Naik
 
 
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
What is the quantity of cement, sand, and gravel to be used in M20 grade of concrete for 1000 x 1000 x 1000 mm of sand (for cement please mention in kilos, and for sand and gravel please mention it in CFT)   6
HOW TO CALCULATE CEMENT REQUIRED FOR M20,M5 GRADE MSEB 6
for 100 sqm cement concret (1:2:4) 4cm thick floor,the quantity of cement required is   3
what is the quantity of cement,sand and aggregate in 600*600*1600 mm in 1:4:8 RPG 8
consumption of cement in p.c.c. a. mix. 1:1:2 b. mix. 1:1.5:3 c. mix. 1:2:4 d. mix. 1:3:6 e. mix. 1:4:8 MSPL 1
In olden days reinforcing bars in concrete are not got rusted even till now. But recently provided steel getting rusted in concrete. what are the probable reasons?   10
what are the Cement Coefficient for Block Work & plastering Work?   1
what is mixing ratio of M25?   13
How find out Rolling margin of steel dia.wise?   3
Why we use Reinforcement out side of the column not in centre   3
if rise and tread of stairs rae 16 & 25cm with landing slab of thickness 100mm . If there are 8steps, and carpenter ask for to mark the bottom of centering of landing on column, what will be the height above floor finished level?   2
How to evaluate the elastic modulus of soil from the plate load test result? for example ..one of test results are here Max. settement =4.56mm(at 900kPa) Residual settlement = 4.02mm Maximum pressure on soil 900kpa Soil bearing capacity 300kpa Plate diameter=300mm Thickness =25mm Soil description =Grey, clayey silty SAND with gravels and rock fragments   1
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com