The window of time recovery of information processing
capabilities is based on the:

A. criticality of the processes affected.

B. quality of the data to be processed.

C. nature of the disaster.

D. applications that are mainframe based.



The window of time recovery of information processing capabilities is based on the: A. criticali..

Answer / guest

Answer: A

The criticality of the processes that are affected by the
disaster is the basis for computing the window of time
recovery. The quality of the data to be processed and the
nature of the disaster are not the basis for determining the
window of time. Being a mainframe application does not of
itself provide a window of time basis.

Is This Answer Correct ?    9 Yes 1 No

Post New Answer

More CISA Certification Interview Questions

Which of the following is a measure of the size of an information system based on the number and complexity of a system?s inputs, outputs and files? A. Function point (FP) B. Program evaluation review technique (PERT) C. Rapid application design (RAD) D. Critical path method (CPM)

2 Answers  


When reviewing a system development project an IS auditor would be PRIMARILY concerned with whether: A. business objectives are achieved. B. security and control procedures are adequate. C. the system utilizes the strategic technical infrastructure. D. development will comply with the approved quality management processes

1 Answers  


Which of the following would be of the LEAST value to an IS auditor attempting to gain an understanding of an organization's IT process? A. IT planning documents with deliverables and performance results B. Policies and procedures relating to planning, managing, monitoring and reporting on performance C. Prior audit reports D. Reports of IT functional activities

1 Answers  


The PRIMARY purpose of undertaking a parallel run of a new system is to: A. verify that the system provides required business functionality. B. validate the operation of the new system against its predecessor. C. resolve any errors in the program and file interfaces. D. verify that the system can process the production load.

2 Answers  


An IS auditor evaluates the test results of a modification to a system that deals with payment computation. The auditor finds that 50 percent of the calculations do not match predetermined totals. Which of the following would MOST likely be the next step in the audit? A. Design further tests of the calculations that are in error. B. Identify variables that may have caused the test results to be inaccurate. C. Examine some of the test cases to confirm the results. D. Document the results and prepare a report of findings, conclusions and recommendations.

1 Answers  






Which of the following would be the BEST population to take a sample from when testing program changes? A. Test library listings B. Source program listings C. Program change requests D. Production library listings

1 Answers  


When assessing the portability of a database application, the IS auditor should verify that: A. a structured query language (SQL) is used. B. information import and export procedures with other systems exist. C. indexes are used. D. all entities have a significant name and identified primary and foreign keys.

1 Answers  


Which of the following would an IS auditor expect to find in a console log? A. Names of system users B. Shift supervisor identification C. System errors D. Data edit errors

1 Answers  


The review of router access control lists should be conducted during a/an: A. environmental review. B. network security review. C. business continuity review. D. data integrity review.

1 Answers  


The PRIMARY advantage of a continuous audit approach is that it: A. does not require an IS auditor to collect evidence on system reliability while processing is taking place. B. requires the IS auditor to review and follow up immediately on all information collected. C. can improve system security when used in time-sharing environments that process a large number of transactions. D. does not depend on the complexity of an organization's computer systems.

3 Answers  


One of the purposes of library control software is to allow: A. programmers access to production source and object libraries. B. batch program updating. C. operators to update the control library with the production version before testing is completed. D. read-only access to source code.

2 Answers  


IS management has recently informed the IS auditor of its decision to disable certain referential integrity controls in the payroll system to provide users with a faster report generator. This will MOST likely increase the risk of: A. data entry by unauthorized users. B. a nonexistent employee being paid. C. an employee receiving an unauthorized raise. D. duplicate data entry by authorized users.

2 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)