ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3113)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3298)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13416)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2382)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (420)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (165)
 Instrumentation interview questions  Instrumentation Interview Questions (2393)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (107)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (78)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1202)
Question
WHAT IS THE DIFFERENCE BETWEEN SHUTTERING & CENTRING
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
shuttering means a shape made before pouring of concrete as
specific size and diamention. This shape is made by
plywood/plate and with proper support.
centring means supporting arrengment of roof slab from
bottom.
 
Is This Answer Correct ?    87 Yes 15 No
Biplab Ghosh
 
Answer
# 2
shuttering means form work for concreting , and centering means proper positioning of reinforcement with shuttering. 
Is This Answer Correct ?    14 Yes 4 No
Joy
 
 
 
Answer
# 3
Shuttering is the frame or base provided for RCC structure
while centering is the support for shuttering.
 
Is This Answer Correct ?    18 Yes 11 No
Devi Singh
 
Answer
# 4
The vertical form work is called shuttering,where as horizontal form work is called as centring. 
Is This Answer Correct ?    20 Yes 15 No
Mohammad Eqbal
 
Answer
# 5
Shuttering is the structure prepared by mostly wood or steel
for pouring of concrete. centring is vertical spports for
withstand that..
 
Is This Answer Correct ?    3 Yes 0 No
Sheik.s
 
Answer
# 6
I Think there is no Difference between the two.. both are
the same..


Formwork is the term given to either temporary or permanent

moulds into which concrete or similar materials are poured.

In the context of concrete construction, the falsework

supports the shuttering moulds.



and same for shuttering also...
 
Is This Answer Correct ?    7 Yes 5 No
Mukarram
 
Answer
# 7
Shuttering is formwork which is used to shape up footing, column, beam , slab as per there given shape and sizes. While centering is process of marking center over actual site as per drawing 
Is This Answer Correct ?    2 Yes 0 No
Satish Ramnath Pekhale
 
Answer
# 8
Centering is define as a proper arrangement of the Shuttering for giving dimension to structure. 
Is This Answer Correct ?    1 Yes 0 No
Nitin Lahane
 
Answer
# 9
shuttering of course is the framework done before concreting but centering is done while shuttering for proper placement.
to construct an arch ...we need to do shuttering perhaps centering.
 
Is This Answer Correct ?    0 Yes 1 No
Devangie
 
Answer
# 10
all vertical surfaces is shuttering and all horizontal
surfaces is centering.
 
Is This Answer Correct ?    0 Yes 1 No
Shenbagaraj.t
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
URGENT: please tell me what's normal drawing scale for residential building and commercial building? Thanks.   5
how much grade of concrete can be used for different structural element such as slab,beam,column,footing & plinth beams? and type of cement can be used in construction work & also types of cemnt grades L&T 2
In case of columns the cover is from main steel or from stirrup & which is the IS code mentioned in it?   2
how to decide the column size and dia of the bar L 1
weight of 32mm rod/m   5
what is a minimum strength recommented for aerocon blocks?   1
what is the yield strength of M30 grade of concrete   1
a revised estimate is prepared when the original estimate has exceed by more than 1 percent 2 10 18.40   2
Why shoring is employed in building industry?   1
what is the difference between weir and a barrage AAI-Airports-Authority-Of-India 10
What is the wastage % of concrete in Conventional shuttering design & Mivan Shuttering for high rise building.   1
Brick size 230X115X150mm, how many bricks, quantity of sand, cement required to construct 10 sq mtrs of 115mm thick brick wall. Feana 2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com