Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3073)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3287)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13324)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2364)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (416)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (79)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (163)
 Instrumentation interview questions  Instrumentation Interview Questions (2375)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (106)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (43)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (75)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1196)
Question
What is the ratio of Grades M10,M15,M20,M25,M30,M35,M40.
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
ratio of M10-1:3:6
M15-1:2:4
M20-1:1.5:3
that rattio is nominal mix basis.above M20,than mix design
is preford.basically M25 consider is 1:1:2
 
Is This Answer Correct ?    303 Yes 27 No
Brajesh Kaurav
 
Answer
# 2
after M25 we have to control the strength acoording to
garde, so it will be disigned
M10- 1:3:6
M15- 1:2:4
M20- 1:1.5:3
M25- 1:1:2
 
Is This Answer Correct ?    227 Yes 24 No
Hyder
 
 
 
Answer
# 3
M-10 - 1:3:6
M-15 - 1:2:4
M-20 - 1:1.5:3
M-25 - 1:1:2
M-30 - M-40 - Design Mix Followed
 
Is This Answer Correct ?    119 Yes 13 No
Venki
 
Answer
# 4
M-5- 1:5:10
M-7.5 -1:4:8
M-10 - 1:3:6
M-15 - 1:2:4
M-20 - 1:1.5:3
M-25 -1:1:2
M-30 - M-40 - Design Mix Followed
 
Is This Answer Correct ?    116 Yes 13 No
Manoj Kumar
 
Answer
# 5
M5 - 1:5:10
M7.5 - 1:4:8
M10 - 1:3:6
M15 - 1:2:4
M20 - 1:1.5:3
M25 - 1:1:2
M30,M35,M40 - Design Mix Followed
 
Is This Answer Correct ?    76 Yes 9 No
Munesh Natrrajan
 
Answer
# 6
m5 = 1:4:8
m10= 1:3:6
m15= 1:2:4
m20= 1:1.5:3
m25= 1:1:2
 
Is This Answer Correct ?    105 Yes 44 No
Vikas
 
Answer
# 7
M-5- 1:5:10
M-7.5 -1:4:8
M-10 - 1:3:6
M-15 - 1:2:4
M-20 - 1:1.5:3
M-25 -1:1:2
 
Is This Answer Correct ?    59 Yes 12 No
Karthik.k
 
Answer
# 8
No where code IS is specified mix ratios for grade of
concrete. But IS 456-2000 table no 9 is given guideline for
nominal mix of grade M5 to M20 by weigh batches.
At the same time all are mentioned mix ratios. Is it weigh
batch or volume batch
 
Is This Answer Correct ?    28 Yes 6 No
Elanthendral M.
 
Answer
# 9
m25 1:1:2
m20 1:1.5:3
m15 1:2:4
m10 1:3:6
 
Is This Answer Correct ?    27 Yes 9 No
Alexander Paul
 
Answer
# 10
M5 1:5:10
M7.5 1:4:8
M10 1:3:6
M15 1:2:4
M20 1:1.5:3
M25 1:1:2
 
Is This Answer Correct ?    8 Yes 2 No
Vtu
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
which tests for concrete pouring period at the site? Al-Turki 5
ratio of rcc 1:1.5:3 grade of concrete ,7days& 14&28 days after curing how much strength of compressive strength in rcc slab   2
Method of findingthe dry ingredient quantity of 1 m3 concrete. L&T 14
What is the graphical relationship between N - Value of soil and Dia. of pile when pile length is fixed, and n - Value and length of pile when its dia. is fixed.   1
point of contraflaxure   1
22. Are you willing to attend trainings, learn new skills and develop as a professional?   2
In case of a beam ,main steel is provided along the longer span because, bending moment is directly proportional to length but why in case of one way slab main steel is provided along shorter span while as bending takes place along longer span?comment Power-Grid 5
beam top main reinforcement(25mm) was drilled off by mistakely when making drill hole for dummy columns. any one can give useful information for this issue or related code or websites.   3
which one is strong? field weld or shop weld? CCCL 6
What are the deshuttering time for Salb Beam Column RCC Wall Footing Staircase L&T 7
Please tell me present is code no for steel structure work. Thanks.   2
what is the yield strength of M30 grade of concrete   1
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   