Answer / mangesh

Make stocks in trapezoidal shape. find out the qty
as h/3(A1+A2+rootof A1A2).A1 top area, A2 bottom area& h is
height.

Is This Answer Correct ?    6 Yes 0 No

How calculate the physical stock of material such as Fine/Coarse aggregate,sand & stone dust l..

Answer / anwar hussain

Collect the material in conical shape,calculate the radius
(r) by measuring the circumferance & hight(H) & use
following formula:

V=0.333 X 3.14 X r2 X H

Where r2 is square of radius and H is Height of

Is This Answer Correct ?    4 Yes 0 No

How calculate the physical stock of material such as Fine/Coarse aggregate,sand & stone dust l..

Answer / jalandar rajgole

Collect the material in conical shape,measure the
circumferance & hight & use following formula:

V=3.14Xr2Xh

Is This Answer Correct ?    7 Yes 5 No

Post New Answer

More Civil Engineering Interview Questions

what is the percentage of silt in black cotton soil.?

0 Answers  


 What is difference between limit state and working stress method? How it is applies in building structure.

0 Answers  


Differentiate orthographic and isometric projections?

0 Answers  


punj loyed and sapurjl palanjl

0 Answers  


how to estimate shuttering form work or how to take off material quantity???

3 Answers  






what is rolling margin of steel

1 Answers   Tata Projects,


What is the amount on nails per bag needed for 1m square of wooden form work?

2 Answers   Ansal Housing, College School Exams Tests,


What is labour rate per kg for cutting,fixing and binding of reinforcement steet..??

3 Answers   GKC Projects Limited GKCPL,


cement constant for brick works

3 Answers  


what is civil all interview questions

0 Answers   Gammon, MGM,


what is diff between auto level and dumpy level?

4 Answers   ABB, L&T, NCCL,


How calculate the water for 1m3 concrete

6 Answers   DLF,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5084)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16631)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1094)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)