wire cannot be actually said how much required for 1ton or
2ton, it actually depends on the design given to in which
the spacing varies so wire required also varies for column
footin and slab. u can just assume a small quanity of wire
to avoid wastage.
The question itself is not a relevant one. Binding wire
quantity varies for different kind of structural members
depending upon the design at different region of the world.
We, at UAE 've a thumb rule to estimate for this to
consider as the 2% of total quantity of steel for the
perticular project.And it worked out approximately correct
for the almost of all projects in my carrier.