ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3078)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3289)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13331)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2363)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (416)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (79)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (163)
 Instrumentation interview questions  Instrumentation Interview Questions (2381)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (106)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (43)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (77)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1196)
Question
how much volume is one bag cement of 50kg
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
volume of one bag cement =0.035m3 
Is This Answer Correct ?    63 Yes 1 No
Arunravi.com
 
Answer
# 2
in meter =.035 cum
in feet =1.25 cuft
 
Is This Answer Correct ?    47 Yes 4 No
Akbar_u2u
 
 
 
Answer
# 3
the voloum is 0.0347=35 liter 
Is This Answer Correct ?    44 Yes 6 No
Renupandey
 
Answer
# 4
35litrs 
Is This Answer Correct ?    45 Yes 17 No
Sachin Ahire
 
Answer
# 5
0.035 cum

for more visit www.arunravi.com
 
Is This Answer Correct ?    15 Yes 3 No
Arun
 
Answer
# 6
1m3 of cement = 1440Kg/m3
then for 50Kg = 50/1440 = 0.0347 m3 per bag
 
Is This Answer Correct ?    12 Yes 0 No
Aaaaa
 
Answer
# 7
To calculate the volume of any bag we need to know the
density. In freshly packed cememt bags the standard density
is 1505 kg/m3).

To know the volume of a 50kg cement bag divide the bag
weight by the density, i.e.:

50 kg 1505 kg/m3 = 0.0332 m3
= 1.1724 Cft
= 33.2 LITRES
 
Is This Answer Correct ?    15 Yes 5 No
Vijay Varma
 
Answer
# 8
one bag of cement i.e. 50kg=34.74 lit. 
Is This Answer Correct ?    8 Yes 5 No
Ravindra Verma
 
Answer
# 9
v=m/d=50/2400(density of cement)=.02 cum 
Is This Answer Correct ?    6 Yes 24 No
Md Sarfaraz Ali
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
how much quantity a skilled labour and unskilled does Pcc per day, if ratio is(1:2:4)   3
what is mean by eccentric footing?   2
NP3 CLASS HUME RCC PIPE   1
why wire mesh is used in plastering   3
what is advantage of vdf flooring ? nsl 1
what is meant by VDF FLOORING? why it is used?   2
what type of waterproofing and procedure using in building? Tulip 1
what is the difference between built-up area & carpet area? how to calculate this areas?as there are any formula to calculate these areas? Dimension-Data 5
How to calculate strirubs hook length? one of my friend said unit of steel*dia of steel*no of bend=hook length is correct r wronge   2
What is meant by End contractions   1
define prestressing? compare prestressing with post tensioning?   1
how quantity of much blocks, cement and sand is required to complete 1sq.m of CC Hollow blockwork L&T 2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com