Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3120)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3299)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13431)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2385)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (420)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (165)
 Instrumentation interview questions  Instrumentation Interview Questions (2398)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (107)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (79)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1203)
Question
how much volume is one bag cement of 50kg
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
volume of one bag cement =0.035m3 
Is This Answer Correct ?    75 Yes 1 No
Arunravi.com
 
Answer
# 2
in meter =.035 cum
in feet =1.25 cuft
 
Is This Answer Correct ?    53 Yes 4 No
Akbar_u2u
 
 
 
Answer
# 3
the voloum is 0.0347=35 liter 
Is This Answer Correct ?    47 Yes 7 No
Renupandey
 
Answer
# 4
35litrs 
Is This Answer Correct ?    47 Yes 17 No
Sachin Ahire
 
Answer
# 5
1m3 of cement = 1440Kg/m3
then for 50Kg = 50/1440 = 0.0347 m3 per bag
 
Is This Answer Correct ?    18 Yes 0 No
Aaaaa
 
Answer
# 6
0.035 cum

for more visit www.arunravi.com
 
Is This Answer Correct ?    15 Yes 3 No
Arun
 
Answer
# 7
To calculate the volume of any bag we need to know the
density. In freshly packed cememt bags the standard density
is 1505 kg/m3).

To know the volume of a 50kg cement bag divide the bag
weight by the density, i.e.:

50 kg 1505 kg/m3 = 0.0332 m3
= 1.1724 Cft
= 33.2 LITRES
 
Is This Answer Correct ?    15 Yes 6 No
Vijay Varma
 
Answer
# 8
one bag of cement i.e. 50kg=34.74 lit. 
Is This Answer Correct ?    10 Yes 5 No
Ravindra Verma
 
Answer
# 9
v=m/d=50/2400(density of cement)=.02 cum 
Is This Answer Correct ?    6 Yes 25 No
Md Sarfaraz Ali
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
coarse sand has a fineness modulus in range of   2
What is the difference between normal brick & concrete hollow blocks in all aspects? L&T 2
A floor has to be removed partially with block work tying floors together, can block work continue on floor that has to removed excluding demolishing works tying floor from underside of slab and top of slab demolishing floor upon completion?   1
how do measure the safe bearing capacity of soil? what is the compresive strength for concret?(max.&min.)   1
1. why we use inverted beam ? 2.why we use extra bar in beam ? 3.dimension in L-bar in column ,footing and beam   2
what is the functional requirement of cement plaster in RCC members & masonry?? Is it Manditory to do plastering on all RCC members(beams, Columns, Slabs)? in what places plasterring could be kept as an optional one???   2
how to calculate no. of bricks for 1 cft? how to calculate cement and sand in cft?   4
WHY DO WE PROVIDE DEVELOPEMENT LENGTH AND EXTRA BARS AT TOP   2
how much solid block in 1m3   3
advantage and dis adventagesof using crusher dust insted of sand in rcc works DLF 3
Explain your project management? Shell 2
what is procedure to find the volume of material in M20 concrete?   5
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   