ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3155)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3310)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13485)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2396)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (424)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (166)
 Instrumentation interview questions  Instrumentation Interview Questions (2409)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (109)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (81)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1207)
Question
what is the shuttering normal clear cover for footings,
walls, beams & columnms
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
Cover Basically Differs From Structure To Structure

Nominally used Covers Are As Follows
Footing -50mm to 75mm
Column- 40mm to 50mm
Beam- 25 mm
Slab- 15mm to 20mm (Minimun cover As Slab thickness Is
usualy Very Low Compare to Other Structural Parts)
 
Is This Answer Correct ?    28 Yes 2 No
Asif
 
Answer
# 2
Concrete cover depends on environmental condition, grade of
concrete, thickness of members, maximum size of aggregate
used etc. Normally cover for footing 75mm, walls 25mm,
beams 25 to 40mm bottom and side and Column 25 to 50mm.
 
Is This Answer Correct ?    14 Yes 4 No
Pradeep
 
 
 
Answer
# 3
for footings 50mm
for columns 40mm
for beams 25mm
for slabs 25mm
 
Is This Answer Correct ?    7 Yes 1 No
Venkateswarlu Vattigunta
 
Answer
# 4
column is 25mm-50mm beam is 40mm slab is 20mm footing is 50mm-75mm 
Is This Answer Correct ?    1 Yes 1 No
Silambarasan
 
Answer
# 5
it depends on different conditions but normally
for columns 20mm
for footings 75mm
for beams 50mm
 
Is This Answer Correct ?    2 Yes 15 No
Naasir
 
Answer
# 6
for footings 50mm
for columns 20mm
for beams and slabs 20mm
 
Is This Answer Correct ?    6 Yes 20 No
Shiva
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
what is thickness of NP2 hume pipe?   3
Hi all, need Staad Pro V8i tutorial Modi-Builders 1
How to calculate numbers of carpenter, fitter, mason, unskilled worker on the basis of built up area or floor plat area of building?   2
what is void ratio??   3
Clarify the out turn of steel fixer in construction field   1
How many number of chairs required per Smt.   3
how to calculate the steel quantity for beams & columns also footing net? what is the formulae for calculate the steel quantity? what is mean by (100.3)plinth level?what is mean by 100.3? explained it?   2
i want to make this calution for making a buliding but i dont know the formula for this and also how much cement concrete an sand use for this calculation,calculation is below(100ft lenths 75ftwidth and 100mm thikness)plz brife the calcution thanks Sobha-Developers 1
how to calculate concrete quantity for footing using M25 grade 1:1:2 for 730cft. Simplex 3
curing duration L&T 5
In olden days reinforcing bars in concrete are not got rusted even till now. But recently provided steel getting rusted in concrete. what are the probable reasons?   10
WHAT IS THE RATE OF EARTHWORK EXCAVATION?   2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com