ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3011)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3270)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13223)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2348)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (407)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (76)
 Bio Engineering interview questions  Bio Engineering Interview Questions (16)
 Metallurgy interview questions  Metallurgy Interview Questions (79)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (162)
 Instrumentation interview questions  Instrumentation Interview Questions (2317)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (104)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (43)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (73)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1189)
Question
what is the shuttering normal clear cover for footings,
walls, beams & columnms
 Question Submitted By :: Sukuvathsal
I also faced this Question!!     Rank Answer Posted By  
 
  Re: what is the shuttering normal clear cover for footings, walls, beams & columnms
Answer
# 1
Concrete cover depends on environmental condition, grade of
concrete, thickness of members, maximum size of aggregate
used etc. Normally cover for footing 75mm, walls 25mm,
beams 25 to 40mm bottom and side and Column 25 to 50mm.
 
Is This Answer Correct ?    12 Yes 4 No
Pradeep
 
  Re: what is the shuttering normal clear cover for footings, walls, beams & columnms
Answer
# 2
for footings 50mm
for columns 20mm
for beams and slabs 20mm
 
Is This Answer Correct ?    6 Yes 19 No
Shiva
 
 
 
  Re: what is the shuttering normal clear cover for footings, walls, beams & columnms
Answer
# 3
it depends on different conditions but normally
for columns 20mm
for footings 75mm
for beams 50mm
 
Is This Answer Correct ?    1 Yes 14 No
Naasir
 
  Re: what is the shuttering normal clear cover for footings, walls, beams & columnms
Answer
# 4
Cover Basically Differs From Structure To Structure

Nominally used Covers Are As Follows
Footing -50mm to 75mm
Column- 40mm to 50mm
Beam- 25 mm
Slab- 15mm to 20mm (Minimun cover As Slab thickness Is
usualy Very Low Compare to Other Structural Parts)
 
Is This Answer Correct ?    24 Yes 2 No
Asif
 
  Re: what is the shuttering normal clear cover for footings, walls, beams & columnms
Answer
# 5
for footings 50mm
for columns 40mm
for beams 25mm
for slabs 25mm
 
Is This Answer Correct ?    6 Yes 1 No
Venkateswarlu Vattigunta
 
  Re: what is the shuttering normal clear cover for footings, walls, beams & columnms
Answer
# 6
column is 25mm-50mm beam is 40mm slab is 20mm footing is 50mm-75mm 
Is This Answer Correct ?    1 Yes 1 No
Silambarasan
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
How many kilograms of sand required in cufic feet for one cubic meter of M25 grade concrete JSW 3
Define slump in terms of slump test   6
Can anybody please tell the procedure to calculate the quantity of admixture in Self Compacted COncrete??   1
What is the Steel bar spacing formula for Concrete Slab? B-L-Kashyap 3
what is the difference between ribbed steel & tor Steel ?   1
how many cement bags in 1m^3 cement concrete in all grade Amara-Raja 7
what is difference between fe 415 and fe 500 CCCL 7
Concrete how muvh strenght gain 7days,14day,s,21day's,28day's&56day's after curing   3
difference between MS rod & TMT rod?   3
how to test the quality of bars???   6
father of soil mechanics   8
1)What is swear, swage and storm water? 2)What are the sizes of bricks based on Nominal, practical and standard? 3) What is the distinguies between the grade of cement 43, 53? L&T 4
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com