Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3157)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3309)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13489)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2396)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (424)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (166)
 Instrumentation interview questions  Instrumentation Interview Questions (2409)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (109)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (82)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1211)
Question
methode of psc girder stressing
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
Generally In a prestressed COncrete Girder Stresing is done
using multi pull jacks that can pull all the cables in a
seething pipe. Also jacks are provided on both the ends of
cables and stress is applied to it until it reaches the
specified limit.
Elongation of the cables is also measured to cross check
the tension in the cables.
 
Is This Answer Correct ?    39 Yes 2 No
Dushyant Bansal
 
Answer
# 2
order in which cables are pulled n psc girder shall be explained.after casting of girder,after how many days and in which order cable shall be pulled.
regards
satya pal
 
Is This Answer Correct ?    5 Yes 7 No
Satya Pal
 
 
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
Slow setting admixture is used in mass concrete because of Reliance 4
what is the least-count of plane- table,dumpy,theodolite,compass,tachometer? L&T 3
9*9m 1:4:8 ratio using what quantity of 40mm aggregate, sand&cement please tell anwser L&T 3
a simple instrument used for the measurement of colour in water is called   7
what is water cement ratio m10,m15,m20,m25,m30,m35m ,m40 JK-Cement 7
why there is no concrete mix of ratio 1:.5:1   2
cross hairs in surveying telescope are fitted in the objective lense at the center of the telescope at the optical centre of eyepiece in front of the eyepiece   2
What is the difference between stress and strength?   13
how much quantity of paint is required for 1 square meter wall for single and double coat..?   1
what is the m20 grade concrete ingredients?   2
what is meant by civil engineer?   2
Dear sir, What is the procedure for total station?How to calculate? L&T 2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com