ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3129)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3300)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13439)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2385)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (420)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (165)
 Instrumentation interview questions  Instrumentation Interview Questions (2401)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (107)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (80)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1203)
Question
how do we calculate wastage of steel in the site,what r the 
items to taken into account for wastage calculation?
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
wsstage calculation vary from large dia to small dia.
up to 20% we are taken 2.5%
above 20 dia we are calculate as 5%
 
Is This Answer Correct ?    16 Yes 3 No
Sjtbehera
 
Answer
# 2
Wastage= Actual consumed-Theoretical consumption

% Wastage=(Actual consumed-Theoretical
consumption)x100/Actual consumed


Actual Consumed= Total issue- (Stock at site+ Scrap)

Total Issue = (Total qty Received from Market+received from
other sites-Total qty dispatched to other sites)(+/-)rolling
margin
 
Is This Answer Correct ?    6 Yes 0 No
Pr
 
 
 
Answer
# 3
total quantity of steel*5% 
Is This Answer Correct ?    8 Yes 4 No
Monu Lal
 
Answer
# 4
2% of the project only 
Is This Answer Correct ?    0 Yes 7 No
Anoop Didwnaiya
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
What is the unit weight of cement?   1
What is water/cement ratio? Importance in construction?   1
What is the diffrence between plinth/basement and plot area   1
among fine,coarse sand which is used for plaster, brickwork and RCC & why?   1
What is the difference between M20 and M25 concrete? L&T 6
why you want more salary here then previous company??? TATA 3
why elongation index is not required for concreteing coarse aggregate..   2
In which code or text book can i get the reinforcement detailing for slabs, beams, columns.   5
Typical floor design load in Residential Building----------- -----   2
how to convert sand from Cum to Brass   2
What is the ring size of column 600x400 (8mm dia ring) ? Simplex 11
Approximate weight of a modular brick?   1
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com