info       Did you received any Funny E-Mails from your Friends and like to share with rest of our friends? Yeah!! you can post that stuff   HERE
Google
   
 
Categories  >>  Engineering  >>  Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions
 Electrical Engineering interview questions  Electrical Engineering Interview Questions
 Electronics Communications interview questions  Electronics Communications Interview Questions
 Chemical Engineering interview questions  Chemical Engineering Interview Questions
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions
 Bio Engineering interview questions  Bio Engineering Interview Questions
 Metallurgy interview questions  Metallurgy Interview Questions
 Industrial Engineering interview questions  Industrial Engineering Interview Questions
 Instrumentation interview questions  Instrumentation Interview Questions
 Automobile Engineering interview questions  Automobile Engineering Interview Questions
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions
 Marine Engineering interview questions  Marine Engineering Interview Questions
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions
 Engineering AllOther interview questions  Engineering AllOther Interview Questions
Question
how to calculate quantities of sand , cement & aggregate in 
1m3 - M20 , 1m2 of 6mm/12mm/20mm plaster , 1m3 20cm/ 1m2 of 
10cm brick wall, paint quantity for 1m2 snowcem and lime 
painting?
 Question Submitted By :: Rohit_rangnekar1975
I also faced this Question!!     Rank Answer Posted By  
 
  Re: how to calculate quantities of sand , cement & aggregate in 1m3 - M20 , 1m2 of 6mm/12mm/20mm plaster , 1m3 20cm/ 1m2 of 10cm brick wall, paint quantity for 1m2 snowcem and lime painting?
Answer
# 1
1. Grade of concrete M20 so ratio is 1:11/2:3
let volume of concrete - 1cum
total ratio- 1+1.5+3 = 5.5
cement = 1x15.4/5.5 = 2.8 cum so cement is =2.8/.347=8 bags
sand-2.8*1.5= 4.2cum
aggregate- 2.8*3= 8.4 cum

2. plaster = suppose 12mm palster
consider 1 sqm ratio is 1:6
volume of concrete= .012x1= .012cum ( per 1sqm)
incrase 20% for joint, filling and wastage=.012*20%=.0144

calculate 1/3rd of mortar when
dry= .0144*1/3+.0144= .0192cum

summation of ratio=7 so cement= .0192/7=.00274cum
= .0789bags
sand= .00274*6=.0164cum

this formula applied for 6mm and 20mm also.
plaster area= paint area
 
Is This Answer Correct ?    32 Yes 29 No
Sjtbehera
[Hari Machines]
 
  Re: how to calculate quantities of sand , cement & aggregate in 1m3 - M20 , 1m2 of 6mm/12mm/20mm plaster , 1m3 20cm/ 1m2 of 10cm brick wall, paint quantity for 1m2 snowcem and lime painting?
Answer
# 2
1. Grade of concrete M20 so ratio is 1:11/2:3
let volume of concrete - 1cum
total ratio- 1+1.5+3 = 5.5
cement = 1x1.54/5.5 = 0.28 cum so cement is =0.28x
1440Kg/cum = 403.2 Kg = 8.064 bags
sand-0.28*1.5= 0.42cum
aggregate- 2.8*3= 0.84 cum

2. plaster = suppose 12mm palster
consider 1 sqm ratio is 1:6
volume of concrete= .012x1= .012cum ( per 1sqm)
incrase 20% for joint, filling and wastage=.012*20%=.0144

calculate 1/3rd of mortar when
dry= .0144*1/3+.0144= .0192cum

summation of ratio = 7
cement= .0192/7=.00274cum
= .0789bags
sand= .00274*6=.0164cum

this formula applied for 6mm and 20mm also.
plaster area= paint area
 
Is This Answer Correct ?    41 Yes 13 No
V.purushotham
 
 
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
Diversion of cum to cft  7
what is the detention period for oxidation ponds  2
What is the dimension of Slump cone which is used to measure the Slump value of concrete? Slump value for Pile concrete? Slab concrete? Column concrete?  3
how can we determine the quantity of steel bars in a structure? is there any formula for determing the number of bars required ?  2
Why alternate bars are given bent-up in slab and how to decide the length of bent up?  3
what is scaffolding and state is purpose  6
we are roofing contractors,we are filling a bill in work contract 4.12% method, we collecting 4.12% from our customer but every month we have been paying the vat at 2% from our pocket on the total value of bill. our auditor told me the above method do not collect 2% from the customer side is it true?  1
how we can calculate a bentup hook in difreeent angles.for exp.at 90 degree,45degree,60 degree.. Gammon2
why cutting length in design of beam is rounded more for -r/f & less for for +r/f  1
Whr is use tierod???what is standard size of it Orbit-Corporation2
What is a Quick Sand?  3
which type of foundation is used for seismic prone area? Kerala-Public-Service-Commission9
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   