ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
tip   To Refer this Site to Your Friends   Click Here
Google
   
 
Categories  >>  Engineering  >>  Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions
 Electrical Engineering interview questions  Electrical Engineering Interview Questions
 Electronics Communications interview questions  Electronics Communications Interview Questions
 Chemical Engineering interview questions  Chemical Engineering Interview Questions
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions
 Bio Engineering interview questions  Bio Engineering Interview Questions
 Metallurgy interview questions  Metallurgy Interview Questions
 Industrial Engineering interview questions  Industrial Engineering Interview Questions
 Instrumentation interview questions  Instrumentation Interview Questions
 Automobile Engineering interview questions  Automobile Engineering Interview Questions
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions
 Marine Engineering interview questions  Marine Engineering Interview Questions
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions
 Engineering AllOther interview questions  Engineering AllOther Interview Questions
Question
how is the wastage component in structural steel being 
considered while doing the reconcillation for the 
fabrication with returning of scrap under 1 meter length
 Question Submitted By :: Mishra
I also faced this Question!!     Rank Answer Posted By  
 
  Re: how is the wastage component in structural steel being considered while doing the reconcillation for the fabrication with returning of scrap under 1 meter length
Answer
# 1
wastage is considered as 5% in a metric ton. 
Is This Answer Correct ?    7 Yes 4 No
Sandip Panda
 
  Re: how is the wastage component in structural steel being considered while doing the reconcillation for the fabrication with returning of scrap under 1 meter length
Answer
# 2
as per indian standards only 3% wastage is allowed
out of this 2 % is considerable and 1 % in non considerable
 
Is This Answer Correct ?    17 Yes 0 No
Dushyant Bansal
 
 
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
what is the slump of pile concreting work? give me the value of minimum and maximum value of slump and how give slump in pile?  2
by which IS Code bend correction is two times of the dia meter of steel is taken  3
why canot DBM is continue as surface coarse insted of BC? what is dieefrence between DBM & BC?  1
Allowable wastage for ready mix concrete? L&T3
HOW MUCH WASTAGE WE CONSEDERED FOR CEMENT & STEEL L&T2
among fine,coarse sand which is used for plaster, brickwork and RCC & why?  1
Tell me about Construction, Contraction and Expansion joints... Modi-Builders1
what is the density of Coarse Aggregate in 1 cu m of Concrete?  6
1M2=how much M3?  4
whta are the types of columns  2
Can i have pumpable mix design for M10 concrete without fly ash with OPC 43G cement?  1
what"s the formula find the cement consumption for brick work 12 thick wall 1 m2? KIMS2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Help  |  Site Map 1  |  Articles  |  Site Map  |   Site Map  |  Contact Us interview questions urls   External Links 
   
Copyright © 2012  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  Forum9.com   ::  KalAajKal.com