ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3151)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3304)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13476)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2395)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (424)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (17)
 Metallurgy interview questions  Metallurgy Interview Questions (80)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (166)
 Instrumentation interview questions  Instrumentation Interview Questions (2407)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (111)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (45)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (81)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1205)
Question
1) One mason per day how many cu.m work will do as per list 
given a) Brick work,hollow brick work and cc block work and 
plastering how many m2 per day 2) one carpenter per day how 
many m2 will do as well as scaffolding how many m3
 Question Submitted By :: Civil-Engineering
I also faced this Question!!     Answer Posted By  
 
Answer
# 1
one mason bricks works in foundation and plinth level with
cement motor = 1.25m3 per day
bricks works in structure with cement motor =1.00m3 per day
plastering in a one days=10 m2 per days
 
Is This Answer Correct ?    92 Yes 16 No
Matu Singh Chauhan
 
Answer
# 2
Plastering per day 8 hours one mason and helper will cover 10 m2 
Is This Answer Correct ?    23 Yes 4 No
Gowrishankar
 
 
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
how can we find out the ratio of cement and sand in plastering   2
What is steel requirement for one cum concrete   3
qube strenth in 7nth days test IVRCL 10
WHAT IS THE PERMISSIBLE LIMIT OF SILT CONTAIN IN SAND FOR RCC WORK? Ambuja 5
what is correct temperature for pouring concrete?   3
if there is no alternative of silty sand avail near ,then how it is used in cement mortar or concreting?   1
how can we calculate cutting length of a column ring (300 x 600) vardhman 5
# 1. size of the Bricks # 2. Minimum Crushing Strength of Bricks Brigade 5
What is the strength of normal brick in india   2
kindly tell me name of a book to calculate bbs?   2
OPC 43 OR PPC for rcc structures(raft foundation,column etc)? For M20,,which cement is better and why? for a residential structure (3 storey plus basement)   3
WHAT IS DIFFERANCE BEWTWEEN NP2 AND NP3 OF RCC HUME PIPE?   2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com