ALLInterview.com :: Home Page            
 Advertise your Business Here     
Browse  |   Placement Papers  |   Company  |   Code Snippets  |   Certifications  |   Visa Questions
Post Question  |   Post Answer  |   My Panel  |   Search  |   Articles  |   Topics  |   ERRORS new
   Refer this Site  Refer This Site to Your Friends  Site Map  Bookmark this Site  Set it as your HomePage  Contact Us     Login  |  Sign Up                      
Google
   
 
Categories >> Engineering >> Civil Engineering
 
 


 

 
 Civil Engineering interview questions  Civil Engineering Interview Questions (3015)
 Mechanical Engineering interview questions  Mechanical Engineering Interview Questions (3272)
 Electrical Engineering interview questions  Electrical Engineering Interview Questions (13227)
 Electronics Communications interview questions  Electronics Communications Interview Questions (2349)
 Chemical Engineering interview questions  Chemical Engineering Interview Questions (407)
 Aeronautical Engineering interview questions  Aeronautical Engineering Interview Questions (77)
 Bio Engineering interview questions  Bio Engineering Interview Questions (16)
 Metallurgy interview questions  Metallurgy Interview Questions (79)
 Industrial Engineering interview questions  Industrial Engineering Interview Questions (162)
 Instrumentation interview questions  Instrumentation Interview Questions (2319)
 Automobile Engineering interview questions  Automobile Engineering Interview Questions (104)
 Mechatronics Engineering interview questions  Mechatronics Engineering Interview Questions (38)
 Marine Engineering interview questions  Marine Engineering Interview Questions (43)
 Power Plant Engineering interview questions  Power Plant Engineering Interview Questions (73)
 Engineering AllOther interview questions  Engineering AllOther Interview Questions (1190)
Question
plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work
(1sqM)?
 Question Submitted By :: Mzbsacet
I also faced this Question!!     Rank Answer Posted By  
 
  Re: plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work (1sqM)?
Answer
# 1
Hi,
Question is not correct. RCC or PCC cost will be depending
upon the grade of concrete. If PCC is M10 (1:3:6) and if it
RMC (Ready Mix Concrete) cost will be about 3500 Rupees per
Cum and RCC of M20 or 25 cost may not differ much may be
around 4250 more or less. Brick cost will 3000 Rupees per
Cum.
 
Is This Answer Correct ?    40 Yes 12 No
Siva Rami Reddy
 
  Re: plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work (1sqM)?
Answer
# 2
cost of M30 (RMC) = [2700 + cost of cement]/cum
generally 1 cum contained 8 to 11 cement bags
 
Is This Answer Correct ?    21 Yes 11 No
Vkg
 
 
 
  Re: plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work (1sqM)?
Answer
# 3
If PCC is M10 (1:3:6) cost will be about 3000 Rupees per
Cum and RCC of M20 or 25 cost around 4500. Brick cost will
be depend upon brick rate if brick Rs 3 per no. then cost
3000 Rupees per Cum.
 
Is This Answer Correct ?    13 Yes 9 No
Ehaque9499
[M/S Samiah International Builders Pvt. L]
 
  Re: plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work (1sqM)?
Answer
# 4
Rate of RCC (M20) (Foundation) = 4900 / cum
Rate of PCC = 3500 / cum
Brick work = 450/ Sqm
 
Is This Answer Correct ?    25 Yes 6 No
Aparajita Swain
 
  Re: plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work (1sqM)?
Answer
# 5
If PCC is M10 (1:3:6) cost will be about 3500 Rupees per
Cum and RCC of M20 or 25 cost around 4800. Brick cost will
be depend upon brick rate if brick Rs 3 per no. then cost
3200 Rupees per Cum.
 
Is This Answer Correct ?    9 Yes 2 No
Rajeeb Lochan Rout
 
  Re: plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work (1sqM)?
Answer
# 6
p.c.c & r.c.c mix ratio is not given.in case p.c.c m10 &
r.c.c m20. the rate will be changed from site condition and
sorrunding the area how much cost price in raw materials
which type of cement we will used in r.c.c & p.c.c
 
Is This Answer Correct ?    12 Yes 0 No
Vignesh
 
  Re: plz give me the rate of RCC(1cuM), PCC(1 cuM), Brick Work (1sqM)?
Answer
# 7
rcc for per cum
rate 4750
pcc per cum rate
25000
brick work rate per sqm 4000
 
Is This Answer Correct ?    4 Yes 3 No
Amitkumarkushwaha
 

 
 
 
Other Civil Engineering Interview Questions
 
  Question Asked @ Answers
 
is there zone 6 for earthquake in india? on what basis the naming of the zones are done in variuos countries?   1
What is the maximum distance between the stirrups?   10
convert= kg into brass   6
what is superbuilt-up area in flats & how it is calculate?   4
1.WHERE THE SLAG CEMENT IS MAINLY USED. 2.FOR GOOD CONCRETE MIX OF M20 GRADE , CAN IT BE USED? 3. I WE USE FOR BRICKWORLiK AND PLASTERING ANY DISADVANTAGES?E   2
What is the cement and sand content in the mortar used to build 1 sqm of 190x190x390mm hollow and solid blockworks?   1
how many moisture content in well seasoned timber   1
how to calculate water cement ratio? Sobha-Developers 6
when will the position neutral axis shifted in beams   2
What is the difference in Cement content for M-20 Concrete if y ou use OPC & PPC? What is the difference in the Curing Period?   1
how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 digree bents plz tell me if there is any formula or tabel to find it L&T 10
what type of surveying is used for inaccessible area?? RITES 2
 
For more Civil Engineering Interview Questions Click Here 
 
 
 
 
 


   
Copyright Policy  |  Terms of Service  |  Articles  |  Site Map  |  RSS Site Map  |  Contact Us
   
Copyright 2013  ALLInterview.com.  All Rights Reserved.

ALLInterview.com   ::  KalAajKal.com