The building has 12 columns of 12x9 in 3 rows of 4 each in a plot of 50'x30', The central row is strengthened with 16mm twisted rods. The roof area is 1500 sft including balconies. calculate the load factor per sft. Also indicate the number of roofs the building can withstand.
2275what is tmc ,term is used in measureing water, pls tell me 1 tmc = how many litres?
College School Exams Tests, Irrigation, IT Consulting Services, IVRCL,
18 231730Bitumen grades are 30-40,60-70, 80-100. what is mean by 30- 40
ACC, Awasthi Construction, Bitulink, Mir Akhter Hossain, SOT,
10 91345what will be the quantity of matterial and water for pcc in 1 cubic meter , the ratio is 1:4:8 (cement:sand:aggr) ?
3 14134how much cement,sand,aggregate will use for 1 cum in ratio of 1:2:4.
ARS, College School Exams Tests, Gulf Construction, HRL, mWorkspace, NCC, URC Construction,
16 115195Post New Civil Engineering Questions
sir please send me campus placement questions in civil engineering
explain fie benefits of using standard terminology in the measurement process
what r the precaution for high in atp tempareture,low in atp tempareture
how u design STAGING for Superstructure in BRIDGE construction?
What is the snap size in civil and how can we create it?
How many square meter can a worker/labor demolish a structure per day?
why steel tanks are provided (a) for water pressure (b) for wind pressure (c) for earthquake pressure
In a concrete grade C35A, C & A stands for what and equalent cube strength?
what is the difference between prime coat and tack coat in road construction
What are the composition of a landfill?
what is that one cub metre plaster in cemant and fine sand
Does degree of bend of rebars has any effect on strength of the member? For example- if a beam is designed with 45 degree bent up bar with respect to architechtural needs and is not 45 in practical so will there be any reduction in the strength of member?
Where will be the maximum bending moment in a TEE Beam?
Normally in slabs, steel quantity is not added when you calculating concrete quantity for that slab, why it is not added ?
On what basis we decide the formation level of the road? other then that of 50% Cutting and 50% Filling??